Rivo construction progress
Rivo in Dubai Land Residence Complex is 7.0% built at the Land Department inspection of August 2026. Developer Grovy Homes Real Estate Development. Completion registered for December 2027.
7.0%
Built, at the Land Department site inspection of 6 August 2026
Running behind its date
- Completion date (Land Department)
- December 2027
- Finish at recent pace
- February 2039
- Construction started
- November 2025
- Registered with the Land Department
- November 2025
- Developer
- Grovy Homes Real Estate Development
- Community
- Dubai Land Residence Complex
- Units
- 133
- Escrow bank
- Mashreq Bank
- Name in Arabic
- ريفو
- Land Department project number
- 4004
- Land Department site inspections
- 3
Schedule
Between August 2025 and August 2026 the site added about 0.6 points a month. At that rate it would finish around February 2039, more than three months after the December 2027 date registered with the Land Department.
Site inspections
6 August 2026
7.0%+0.4 pts
30 March 2026
6.6%+6.6 pts
26 August 2025
0%
Context
Dubai Land Residence Complex has 65 projects under construction, 24% built on average.
Grovy Homes Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Rivo?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Rivo be completed?
- The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around February 2039. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Rivo is built?
- 7.0%, measured at the Land Department site inspection on 6 August 2026. The Land Department engineers have inspected the site 3 times since August 2025.
- Is Rivo delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Rivo?
- The registered developer is Grovy Homes Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Rivo?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Coral Isle ResidencesAlso by Grovy Homes Real Estate Development. 7.2%, Due March 2027.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026.
- Ag SquareNearby in Dubai Land Residence Complex. 69%.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.








