Alta View Skyhomes construction progress

Alta View Skyhomes in Jumeirah Village Circle is 5.8% built at the Land Department inspection of September 2026. Developer Object One Real Estate Development. Completion registered for June 2029.

5.8%

Built, at the Land Department site inspection of 16 September 2026

Running behind its date

Completion date (Land Department)
June 2029
Finish at recent pace
February 2036
Construction started
August 2025
Registered with the Land Department
June 2025
Units
507
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
ألتا فيو سكاي هومز
Land Department project number
3842
Land Department site inspections
4

Schedule

Between February 2026 and September 2026 the site added about 0.8 points a month. At that rate it would finish around February 2036, more than three months after the June 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

16 September 2026

5.8%+1.8 pts

  • Alta View Skyhomes construction site, Land Department inspection photo 1, 16 September 2026
  • Alta View Skyhomes construction site, Land Department inspection photo 2, 16 September 2026
  • Alta View Skyhomes construction site, Land Department inspection photo 3, 16 September 2026
  • Alta View Skyhomes construction site, Land Department inspection photo 4, 16 September 2026

4 June 2026

4.1%+4.0 pts

  • Alta View Skyhomes construction site, Land Department inspection photo 1, 4 June 2026
  • Alta View Skyhomes construction site, Land Department inspection photo 2, 4 June 2026
  • Alta View Skyhomes construction site, Land Department inspection photo 3, 4 June 2026
  • Alta View Skyhomes construction site, Land Department inspection photo 4, 4 June 2026

19 February 2026

0.1%+0.1 pts

  • Alta View Skyhomes construction site, Land Department inspection photo 1, 19 February 2026
  • Alta View Skyhomes construction site, Land Department inspection photo 2, 19 February 2026
  • Alta View Skyhomes construction site, Land Department inspection photo 3, 19 February 2026

17 June 2025

0%

  • Alta View Skyhomes construction site, Land Department inspection photo 1, 17 June 2025
  • Alta View Skyhomes construction site, Land Department inspection photo 2, 17 June 2025

All 15 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average. Alta View Skyhomes is behind that average.

Object One Real Estate Development has 13 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Alta View Skyhomes?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Alta View Skyhomes be completed?
The completion date registered with the Dubai Land Department is June 2029. At the pace of its recent inspections the site would reach 100% around February 2036. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Alta View Skyhomes is built?
5.8%, measured at the Land Department site inspection on 16 September 2026. The Land Department engineers have inspected the site 4 times since June 2025.
Is Alta View Skyhomes delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2029.
Who is building Alta View Skyhomes?
The registered developer is Object One Real Estate Development. It has 12 other projects under construction in Dubai.
Which bank holds the escrow account for Alta View Skyhomes?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.