Alta View Skyhomes construction progress
Alta View Skyhomes in Jumeirah Village Circle is 5.8% built at the Land Department inspection of September 2026. Developer Object One Real Estate Development. Completion registered for June 2029.
5.8%
Built, at the Land Department site inspection of 16 September 2026
Running behind its date
- Completion date (Land Department)
- June 2029
- Finish at recent pace
- February 2036
- Construction started
- August 2025
- Registered with the Land Department
- June 2025
- Developer
- Object One Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 507
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- ألتا فيو سكاي هومز
- Land Department project number
- 3842
- Land Department site inspections
- 4
Schedule
Between February 2026 and September 2026 the site added about 0.8 points a month. At that rate it would finish around February 2036, more than three months after the June 2029 date registered with the Land Department.
Site inspections
16 September 2026
5.8%+1.8 pts
4 June 2026
4.1%+4.0 pts
19 February 2026
0.1%+0.1 pts
17 June 2025
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average. Alta View Skyhomes is behind that average.
Object One Real Estate Development has 13 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Alta View Skyhomes?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Alta View Skyhomes be completed?
- The completion date registered with the Dubai Land Department is June 2029. At the pace of its recent inspections the site would reach 100% around February 2036. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Alta View Skyhomes is built?
- 5.8%, measured at the Land Department site inspection on 16 September 2026. The Land Department engineers have inspected the site 4 times since June 2025.
- Is Alta View Skyhomes delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2029.
- Who is building Alta View Skyhomes?
- The registered developer is Object One Real Estate Development. It has 12 other projects under construction in Dubai.
- Which bank holds the escrow account for Alta View Skyhomes?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- 1wood ResidenceAlso by Object One Real Estate Development. 94%.
- Ozone 1 ResidenceAlso by Object One Real Estate Development. 57%.
- Winner TowerAlso by Object One Real Estate Development. 28%.
- The Fifth TowerAlso by Object One Real Estate Development. 50%, Due July 2026, passed.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)