Alta View Skyhomes construction progress
The registered completion date for Alta View Skyhomes in Jumeirah Village Circle is June 2029. At the last site inspection, in September 2026, it was 5.8% built. The developer is Object One Real Estate Development.
5.8%
Built, at the site inspection of 16 September 2026
Running behind its date
- Registered completion date
- June 2029
- Finish at recent pace
- February 2036
- Construction started
- August 2025
- First registered
- June 2025
- Developer
- Object One Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 507
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- ألتا فيو سكاي هومز
- Project number
- 3842
- Site inspections
- 4
Schedule
Between February 2026 and September 2026 the site added about 0.8 points a month. At that rate it would finish around February 2036, more than three months after its registered date of June 2029.
Site inspections
16 September 2026
5.8%+1.8 pts
4 June 2026
4.1%+4.0 pts
19 February 2026
0.1%+0.1 pts
17 June 2025
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Object One Real Estate Development has 13 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Alta View Skyhomes?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Alta View Skyhomes handover date?
- The registered completion date is June 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Alta View Skyhomes?
- Alta View Skyhomes was 5.8% built at the site inspection on 16 September 2026. The site has been inspected 4 times since June 2025. The Land Department took 15 site photos at its inspections.
- Is Alta View Skyhomes delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2029.
- Who is building Alta View Skyhomes?
- The registered developer is Object One Real Estate Development. It has 12 other projects under construction in Dubai.
- Which bank holds the escrow account for Alta View Skyhomes?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- 1wood ResidenceAlso by Object One Real Estate Development. 94%.
- Ozone 1 ResidenceAlso by Object One Real Estate Development. 57%.
- Winner TowerAlso by Object One Real Estate Development. 36%.
- The Fifth TowerAlso by Object One Real Estate Development. 55%, Due July 2026, passed.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.