Ab Cavalier construction progress

The register lists Ab Cavalier in Jumeirah Village Circle as complete. Its last site inspection on record was in April 2026. The developer is Ab Developers.

100%

Built, at the site inspection of 21 April 2026

Construction complete

Construction started
June 2023
First registered
February 2024
Developer
Ab Developers
Units
165
Escrow bank
Emirates NBD
Name in Arabic
أب كافالير
Project number
2708
Site inspections
5

Schedule

The register lists Ab Cavalier as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

21 April 2026

100%+3.5 pts

  • Ab Cavalier construction site, inspection photo 1, 21 April 2026
  • Ab Cavalier construction site, inspection photo 2, 21 April 2026
  • Ab Cavalier construction site, inspection photo 3, 21 April 2026
  • Ab Cavalier construction site, inspection photo 4, 21 April 2026

12 December 2025

97%+3.8 pts

  • Ab Cavalier construction site, inspection photo 1, 12 December 2025
  • Ab Cavalier construction site, inspection photo 2, 12 December 2025
  • Ab Cavalier construction site, inspection photo 3, 12 December 2025
  • Ab Cavalier construction site, inspection photo 4, 12 December 2025

27 August 2025

93%+17 pts

  • Ab Cavalier construction site, inspection photo 1, 27 August 2025
  • Ab Cavalier construction site, inspection photo 2, 27 August 2025
  • Ab Cavalier construction site, inspection photo 3, 27 August 2025
  • Ab Cavalier construction site, inspection photo 4, 27 August 2025

27 March 2025

75%+71 pts

  • Ab Cavalier construction site, inspection photo 1, 27 March 2025
  • Ab Cavalier construction site, inspection photo 2, 27 March 2025
  • Ab Cavalier construction site, inspection photo 3, 27 March 2025
  • Ab Cavalier construction site, inspection photo 4, 27 March 2025

12 September 2023

4.1%

  • Ab Cavalier construction site, inspection photo 1, 12 September 2023
  • Ab Cavalier construction site, inspection photo 2, 12 September 2023
  • Ab Cavalier construction site, inspection photo 3, 12 September 2023
  • Ab Cavalier construction site, inspection photo 4, 12 September 2023

All 50 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Ab Developers has 1 project under construction in Dubai, none past their registered completion dates.

Own a unit in Ab Cavalier?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Ab Cavalier handover date?
Construction of Ab Cavalier is recorded as complete. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Ab Cavalier?
Ab Cavalier was 100% built at the site inspection on 21 April 2026. The site has been inspected 5 times since September 2023. The Land Department took 50 site photos at its inspections.
Is Ab Cavalier delayed?
The register lists construction as complete.
Who is building Ab Cavalier?
The registered developer is Ab Developers. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Ab Cavalier?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.