Bayview Boulevard construction progress

The registered completion date for Bayview Boulevard in Palm Deira is April 2027. At the last site inspection, in September 2026, it was 55% built. The developer is Ab Developers.

55%

Built, at the site inspection of 11 September 2026

Running behind its date

Registered completion date
April 2027
Finish at recent pace
March 2028
Construction started
July 2023
First registered
April 2025
Developer
Ab Developers
Community
Palm Deira
Units
68
Escrow bank
Emirates NBD
Name in Arabic
بايفيو بوليفارد
Project number
3251
Site inspections
6

Schedule

Between March 2026 and September 2026 the site added about 2.5 points a month. At that rate it would finish around March 2028, more than three months after its registered date of April 2027.

0%25%50%75%100%2024202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

11 September 2026

55%+6.8 pts

  • Bayview Boulevard construction site, inspection photo 1, 11 September 2026
  • Bayview Boulevard construction site, inspection photo 2, 11 September 2026
  • Bayview Boulevard construction site, inspection photo 3, 11 September 2026
  • Bayview Boulevard construction site, inspection photo 4, 11 September 2026

10 June 2026

48%+8.2 pts

  • Bayview Boulevard construction site, inspection photo 1, 10 June 2026
  • Bayview Boulevard construction site, inspection photo 2, 10 June 2026
  • Bayview Boulevard construction site, inspection photo 3, 10 June 2026
  • Bayview Boulevard construction site, inspection photo 4, 10 June 2026

11 March 2026

40%+18 pts

  • Bayview Boulevard construction site, inspection photo 1, 11 March 2026
  • Bayview Boulevard construction site, inspection photo 2, 11 March 2026
  • Bayview Boulevard construction site, inspection photo 3, 11 March 2026
  • Bayview Boulevard construction site, inspection photo 4, 11 March 2026

27 August 2025

22%+7.1 pts

  • Bayview Boulevard construction site, inspection photo 1, 27 August 2025
  • Bayview Boulevard construction site, inspection photo 2, 27 August 2025
  • Bayview Boulevard construction site, inspection photo 3, 27 August 2025
  • Bayview Boulevard construction site, inspection photo 4, 27 August 2025

22 April 2025

15%+15 pts

  • Bayview Boulevard construction site, inspection photo 1, 22 April 2025
  • Bayview Boulevard construction site, inspection photo 2, 22 April 2025
  • Bayview Boulevard construction site, inspection photo 3, 22 April 2025
  • Bayview Boulevard construction site, inspection photo 4, 22 April 2025

9 September 2024

0%

  • Bayview Boulevard construction site, inspection photo 1, 9 September 2024
  • Bayview Boulevard construction site, inspection photo 2, 9 September 2024

All 42 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Own a unit in Bayview Boulevard?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Bayview Boulevard handover date?
The registered completion date is April 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Bayview Boulevard?
Bayview Boulevard was 55% built at the site inspection on 11 September 2026. The site has been inspected 6 times since September 2024. The Land Department took 42 site photos at its inspections.
Is Bayview Boulevard delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
Who is building Bayview Boulevard?
The registered developer is Ab Developers.
Which bank holds the escrow account for Bayview Boulevard?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.