Bayview Boulevard construction progress

Bayview Boulevard in Palm Deira is 55% built at the Land Department inspection of September 2026. Developer Ab Developers. Completion registered for April 2027.

55%

Built, at the Land Department site inspection of 11 September 2026

Running behind its date

Completion date (Land Department)
April 2027
Finish at recent pace
March 2028
Construction started
July 2023
Registered with the Land Department
April 2025
Developer
Ab Developers
Community
Palm Deira
Units
68
Escrow bank
Emirates NBD
Name in Arabic
بايفيو بوليفارد
Land Department project number
3251
Land Department site inspections
6

Schedule

Between March 2026 and September 2026 the site added about 2.5 points a month. At that rate it would finish around March 2028, more than three months after the April 2027 date registered with the Land Department.

0%25%50%75%100%2024202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

11 September 2026

55%+6.8 pts

  • Bayview Boulevard construction site, Land Department inspection photo 1, 11 September 2026
  • Bayview Boulevard construction site, Land Department inspection photo 2, 11 September 2026
  • Bayview Boulevard construction site, Land Department inspection photo 3, 11 September 2026
  • Bayview Boulevard construction site, Land Department inspection photo 4, 11 September 2026

10 June 2026

48%+8.2 pts

  • Bayview Boulevard construction site, Land Department inspection photo 1, 10 June 2026
  • Bayview Boulevard construction site, Land Department inspection photo 2, 10 June 2026
  • Bayview Boulevard construction site, Land Department inspection photo 3, 10 June 2026
  • Bayview Boulevard construction site, Land Department inspection photo 4, 10 June 2026

11 March 2026

40%+18 pts

  • Bayview Boulevard construction site, Land Department inspection photo 1, 11 March 2026
  • Bayview Boulevard construction site, Land Department inspection photo 2, 11 March 2026
  • Bayview Boulevard construction site, Land Department inspection photo 3, 11 March 2026
  • Bayview Boulevard construction site, Land Department inspection photo 4, 11 March 2026

27 August 2025

22%+7.1 pts

  • Bayview Boulevard construction site, Land Department inspection photo 1, 27 August 2025
  • Bayview Boulevard construction site, Land Department inspection photo 2, 27 August 2025
  • Bayview Boulevard construction site, Land Department inspection photo 3, 27 August 2025
  • Bayview Boulevard construction site, Land Department inspection photo 4, 27 August 2025

22 April 2025

15%+15 pts

  • Bayview Boulevard construction site, Land Department inspection photo 1, 22 April 2025
  • Bayview Boulevard construction site, Land Department inspection photo 2, 22 April 2025
  • Bayview Boulevard construction site, Land Department inspection photo 3, 22 April 2025
  • Bayview Boulevard construction site, Land Department inspection photo 4, 22 April 2025

9 September 2024

0%

  • Bayview Boulevard construction site, Land Department inspection photo 1, 9 September 2024
  • Bayview Boulevard construction site, Land Department inspection photo 2, 9 September 2024

All 42 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Own a unit in Bayview Boulevard?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Bayview Boulevard be completed?
The completion date registered with the Dubai Land Department is April 2027. At the pace of its recent inspections the site would reach 100% around March 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Bayview Boulevard is built?
55%, measured at the Land Department site inspection on 11 September 2026. The Land Department engineers have inspected the site 6 times since September 2024.
Is Bayview Boulevard delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
Who is building Bayview Boulevard?
The registered developer is Ab Developers.
Which bank holds the escrow account for Bayview Boulevard?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.