Viewz 1 By Danube construction photos
65 photos from 11 site inspections, newest first. The percentage is how much of Viewz 1 By Danube was built on the day of each visit.
20 October 202666% built
21 July 202650% built
23 April 202640% built
14 January 202630% built
10 October 202525% built
10 July 202521% built
3 April 202514% built
11 December 20246.5% built
6 March 20240.3% built
16 May 20230% built
10 January 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)






.jpeg&w=3840&q=75)






.jpeg&w=3840&q=75)









.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)






.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)



.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)