Uh West By Ellington construction photos

55 photos taken by Dubai Land Department engineers at 7 site inspections, newest first. The percentage is how much of Uh West By Ellington was built on the day of each visit.

11 June 202671% built

10 February 202660% built

30 August 202536% built

10 April 202526% built

4 July 202411% built

14 March 20246.8% built

31 May 20230% built

Back to Uh West By Ellington construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.