46 photos taken by Dubai Land Department engineers at 7 site inspections, newest first. The percentage is how much of Uh East By Ellington was built on the day of each visit.
11 June 202647% built
5 February 202636% built
16 September 202521% built
10 April 202514% built
4 July 20247.2% built
14 March 20242.5% built
31 May 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.