Uh East By Ellington construction photos

46 photos taken by Dubai Land Department engineers at 7 site inspections, newest first. The percentage is how much of Uh East By Ellington was built on the day of each visit.

11 June 202647% built

5 February 202636% built

16 September 202521% built

10 April 202514% built

4 July 20247.2% built

14 March 20242.5% built

31 May 20230% built

Back to Uh East By Ellington construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.