The Grandala construction photos

54 photos from 7 site inspections, newest first. The percentage is how much of The Grandala was built on the day of each visit.

26 October 202691% built

7 August 202686% built

5 May 202663% built

7 January 202640% built

23 September 202520% built

19 June 202515% built

9 May 20240% built

Back to The Grandala construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.