Moonsa Residences construction progress

Moonsa Residences in International City Phase 3 is 95% built at the Land Department inspection of March 2026. Developer Dugasta Properties Development. Completion registered for August 2025.

95%

Built, at the Land Department site inspection of 31 March 2026

14 months past its registered completion date

Completion date (Land Department)
August 2025
Finish at recent pace
May 2026
Construction started
January 2024
Registered with the Land Department
February 2024
Units
93
Escrow bank
Mashreq Bank
Name in Arabic
مساكن مونسا
Land Department project number
2834
Land Department site inspections
4

Schedule

Moonsa Residences was registered to complete in August 2025, 14 months ago, and is still under construction. Over the last year of inspections it has added about 4.8 points a month. Kept at that rate, the site would reach 100% around May 2026.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

31 March 2026

95%+29 pts

  • Moonsa Residences construction site, Land Department inspection photo 1, 31 March 2026
  • Moonsa Residences construction site, Land Department inspection photo 2, 31 March 2026
  • Moonsa Residences construction site, Land Department inspection photo 3, 31 March 2026
  • Moonsa Residences construction site, Land Department inspection photo 4, 31 March 2026

29 September 2025

66%+16 pts

  • Moonsa Residences construction site, Land Department inspection photo 1, 29 September 2025
  • Moonsa Residences construction site, Land Department inspection photo 2, 29 September 2025
  • Moonsa Residences construction site, Land Department inspection photo 3, 29 September 2025
  • Moonsa Residences construction site, Land Department inspection photo 4, 29 September 2025

22 January 2025

50%+25 pts

  • Moonsa Residences construction site, Land Department inspection photo 1, 22 January 2025
  • Moonsa Residences construction site, Land Department inspection photo 2, 22 January 2025
  • Moonsa Residences construction site, Land Department inspection photo 3, 22 January 2025
  • Moonsa Residences construction site, Land Department inspection photo 4, 22 January 2025

4 January 2024

25%

  • Moonsa Residences construction site, Land Department inspection photo 1, 4 January 2024
  • Moonsa Residences construction site, Land Department inspection photo 2, 4 January 2024
  • Moonsa Residences construction site, Land Department inspection photo 3, 4 January 2024
  • Moonsa Residences construction site, Land Department inspection photo 4, 4 January 2024

All 32 site photos, by inspection date

Context

International City Phase 3 has 21 projects under construction, 30% built on average.

Dugasta Properties Development has 7 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Moonsa Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Moonsa Residences be completed?
The completion date registered with the Dubai Land Department is August 2025. At the pace of its recent inspections the site would reach 100% around May 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Moonsa Residences is built?
95%, measured at the Land Department site inspection on 31 March 2026. The Land Department engineers have inspected the site 4 times since January 2024.
Is Moonsa Residences delayed?
Yes. Its registered completion date of August 2025 has passed and the Land Department still lists it as under construction.
Who is building Moonsa Residences?
The registered developer is Dugasta Properties Development. It has 6 other projects under construction in Dubai.
Which bank holds the escrow account for Moonsa Residences?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.