Terra Gardens construction progress
The registered completion date for Terra Gardens is October 2029. At the last site inspection, in November 2026, it was 3.6% built. The developer is Dwtc Emaar.
3.6%
Built, at the site inspection of 4 November 2026
Running behind its date
- Registered completion date
- October 2029
- Finish at recent pace
- December 2037
- Construction started
- April 2026
- First registered
- October 2025
- Developer
- Dwtc Emaar
- Units
- 561
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- تيرا جاردنز
- Project number
- 4160
- Site inspections
- 3
Schedule
Between June 2026 and November 2026 the site added about 0.7 points a month. At that rate it would finish around December 2037, more than three months after its registered date of October 2029.
Site inspections
4 November 2026
3.6%+3.5 pts
8 June 2026
0.1%+0.1 pts
16 October 2025
0%
Context
Dwtc Emaar has 3 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Terra Gardens?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Terra Gardens handover date?
- The registered completion date is October 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Terra Gardens?
- Terra Gardens was 3.6% built at the site inspection on 4 November 2026. The site has been inspected 3 times since October 2025. The Land Department took 10 site photos at its inspections.
- Is Terra Gardens delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2029.
- Who is building Terra Gardens?
- The registered developer is Dwtc Emaar. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Terra Gardens?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Terra HeightsAlso by Dwtc Emaar. 9.1%, Due March 2029.
- Terra WoodsAlso by Dwtc Emaar. 0%, Due March 2030.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.