Terra Gardens construction progress

The registered completion date for Terra Gardens is October 2029. At the last site inspection, in November 2026, it was 3.6% built. The developer is Dwtc Emaar.

3.6%

Built, at the site inspection of 4 November 2026

Running behind its date

Registered completion date
October 2029
Finish at recent pace
December 2037
Construction started
April 2026
First registered
October 2025
Developer
Dwtc Emaar
Units
561
Escrow bank
Dubai Islamic Bank
Name in Arabic
تيرا جاردنز
Project number
4160
Site inspections
3

Schedule

Between June 2026 and November 2026 the site added about 0.7 points a month. At that rate it would finish around December 2037, more than three months after its registered date of October 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

4 November 2026

3.6%+3.5 pts

  • Terra Gardens construction site, inspection photo 1, 4 November 2026
  • Terra Gardens construction site, inspection photo 2, 4 November 2026
  • Terra Gardens construction site, inspection photo 3, 4 November 2026
  • Terra Gardens construction site, inspection photo 4, 4 November 2026

8 June 2026

0.1%+0.1 pts

  • Terra Gardens construction site, inspection photo 1, 8 June 2026
  • Terra Gardens construction site, inspection photo 2, 8 June 2026

16 October 2025

0%

  • Terra Gardens construction site, inspection photo 1, 16 October 2025
  • Terra Gardens construction site, inspection photo 2, 16 October 2025

All 10 site photos, by inspection date

Context

Dwtc Emaar has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Terra Gardens?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Terra Gardens handover date?
The registered completion date is October 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Terra Gardens?
Terra Gardens was 3.6% built at the site inspection on 4 November 2026. The site has been inspected 3 times since October 2025. The Land Department took 10 site photos at its inspections.
Is Terra Gardens delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2029.
Who is building Terra Gardens?
The registered developer is Dwtc Emaar. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Terra Gardens?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.