Expo City Valley construction photos

76 photos taken by Dubai Land Department engineers at 7 site inspections, newest first. The percentage is how much of Expo City Valley was built on the day of each visit.

19 August 202666% built

1 May 202652% built

24 December 202542% built

22 August 202524% built

12 March 20258.3% built

11 December 20230.4% built

27 April 20230% built

Back to Expo City Valley construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.