46 photos from 6 site inspections, newest first. The percentage is how much of Ghaff Land Residence was built on the day of each visit.

13 October 202666% built

15 July 202664% built

5 March 202660% built

11 November 202552% built

1 July 202539% built

26 November 202423% built

Back to Ghaff Land Residence construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.