51 photos from 9 site inspections, newest first. The percentage is how much of The First Collection At Dubai Sports City was built on the day of each visit.

21 September 202666% built

19 June 202659% built

3 March 202640% built

29 October 202528% built

20 June 202521% built

12 March 202515% built

4 December 202410% built

28 June 20245.1% built

2 November 20230% built

Back to The First Collection At Dubai Sports City construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.