Vitalia By Pinnacle construction progress
Vitalia By Pinnacle in Palm Jumeirah was registered to complete in June 2026 and is still under construction. At the last site inspection, in November 2026, it was 21% built. The developer is Pinnacle A K S Real Estate Development.
21%
Built, at the site inspection of 4 November 2026
5 months past its registered completion date
- Registered completion date
- June 2026
- Finish at recent pace
- August 2030
- Construction started
- July 2024
- First registered
- June 2024
- Developer
- Pinnacle A K S Real Estate Development
- Community
- Palm Jumeirah
- Units
- 45
- Escrow bank
- Mashreq Bank
- Name in Arabic
- فيتاليا من بيناكل
- Project number
- 3022
- Site inspections
- 6
Schedule
Vitalia By Pinnacle was registered to complete in June 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 1.7 points a month. Kept at that rate, the site would reach 100% around August 2030.
Site inspections
4 November 2026
21%+9.1 pts
30 June 2026
12%+5.6 pts
17 February 2026
6.7%+4.2 pts
14 October 2025
2.4%
26 May 2025
2.4%+2.4 pts
1 May 2024
0%
Context
Palm Jumeirah has 16 projects under construction, 45% built on average.
Pinnacle A K S Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Vitalia By Pinnacle?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Vitalia By Pinnacle handover date?
- The registered completion date was June 2026, and the register still lists Vitalia By Pinnacle as under construction. At the pace of its recent inspections the site would reach 100% around August 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Vitalia By Pinnacle?
- Vitalia By Pinnacle was 21% built at the site inspection on 4 November 2026. The site has been inspected 6 times since May 2024. The Land Department took 27 site photos at its inspections.
- Is Vitalia By Pinnacle delayed?
- Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
- Who is building Vitalia By Pinnacle?
- The registered developer is Pinnacle A K S Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Vitalia By Pinnacle?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- SartoriaAlso by Pinnacle A K S Real Estate Development. 51%, Due October 2027.
- Palm Beach Towers -1Nearby in Palm Jumeirah. 83%, Due December 2026.
- Palm Beach Towers - 2Nearby in Palm Jumeirah. 82%, Due December 2026.
- Palm Beach Towers -3Nearby in Palm Jumeirah. 74%, Due December 2026.
- Orla By OmniyatNearby in Palm Jumeirah. 70%, Due December 2026.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)