Vitalia By Pinnacle construction progress

Vitalia By Pinnacle in Palm Jumeirah was registered to complete in June 2026 and is still under construction. At the last site inspection, in November 2026, it was 21% built. The developer is Pinnacle A K S Real Estate Development.

21%

Built, at the site inspection of 4 November 2026

5 months past its registered completion date

Registered completion date
June 2026
Finish at recent pace
August 2030
Construction started
July 2024
First registered
June 2024
Developer
Pinnacle A K S Real Estate Development
Community
Palm Jumeirah
Units
45
Escrow bank
Mashreq Bank
Name in Arabic
فيتاليا من بيناكل
Project number
3022
Site inspections
6

Schedule

Vitalia By Pinnacle was registered to complete in June 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 1.7 points a month. Kept at that rate, the site would reach 100% around August 2030.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

4 November 2026

21%+9.1 pts

  • Vitalia By Pinnacle construction site, inspection photo 1, 4 November 2026
  • Vitalia By Pinnacle construction site, inspection photo 2, 4 November 2026
  • Vitalia By Pinnacle construction site, inspection photo 3, 4 November 2026
  • Vitalia By Pinnacle construction site, inspection photo 4, 4 November 2026

30 June 2026

12%+5.6 pts

  • Vitalia By Pinnacle construction site, inspection photo 1, 30 June 2026
  • Vitalia By Pinnacle construction site, inspection photo 2, 30 June 2026
  • Vitalia By Pinnacle construction site, inspection photo 3, 30 June 2026
  • Vitalia By Pinnacle construction site, inspection photo 4, 30 June 2026

17 February 2026

6.7%+4.2 pts

  • Vitalia By Pinnacle construction site, inspection photo 1, 17 February 2026
  • Vitalia By Pinnacle construction site, inspection photo 2, 17 February 2026
  • Vitalia By Pinnacle construction site, inspection photo 3, 17 February 2026

14 October 2025

2.4%

  • Vitalia By Pinnacle construction site, inspection photo 1, 14 October 2025
  • Vitalia By Pinnacle construction site, inspection photo 2, 14 October 2025
  • Vitalia By Pinnacle construction site, inspection photo 3, 14 October 2025
  • Vitalia By Pinnacle construction site, inspection photo 4, 14 October 2025

26 May 2025

2.4%+2.4 pts

  • Vitalia By Pinnacle construction site, inspection photo 1, 26 May 2025
  • Vitalia By Pinnacle construction site, inspection photo 2, 26 May 2025
  • Vitalia By Pinnacle construction site, inspection photo 3, 26 May 2025
  • Vitalia By Pinnacle construction site, inspection photo 4, 26 May 2025

1 May 2024

0%

  • Vitalia By Pinnacle construction site, inspection photo 1, 1 May 2024
  • Vitalia By Pinnacle construction site, inspection photo 2, 1 May 2024

All 27 site photos, by inspection date

Context

Palm Jumeirah has 16 projects under construction, 45% built on average.

Pinnacle A K S Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Vitalia By Pinnacle?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Vitalia By Pinnacle handover date?
The registered completion date was June 2026, and the register still lists Vitalia By Pinnacle as under construction. At the pace of its recent inspections the site would reach 100% around August 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Vitalia By Pinnacle?
Vitalia By Pinnacle was 21% built at the site inspection on 4 November 2026. The site has been inspected 6 times since May 2024. The Land Department took 27 site photos at its inspections.
Is Vitalia By Pinnacle delayed?
Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
Who is building Vitalia By Pinnacle?
The registered developer is Pinnacle A K S Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Vitalia By Pinnacle?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.