Lime Light Twin Towers construction photos
162 photos from 17 site inspections, newest first. The percentage is how much of Lime Light Twin Towers was built on the day of each visit.
2 April 202671% built
24 November 202570% built
18 January 202170% built
16 August 202070% built
19 November 201969% built
21 February 201968% built
24 December 201868% built
16 July 201867% built
21 January 201865% built
5 September 201762% built
15 March 201761% built
16 October 201648% built
21 April 201644% built
29 November 201540% built
6 May 201536% built
23 November 201431% built
15 July 201421% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.