Elite 10 Sports Residence construction progress

The register lists Elite 10 Sports Residence in Dubai Sports City as complete, with a registered completion date of December 2017. Its last site inspection on record was in December 2017. The developer is Range 4 Developments.

100%

Built, at the site inspection of 25 December 2017

Construction complete

Registered completion date
December 2017
Construction started
October 2014
First registered
November 2014
Developer
Range 4 Developments
Units
800
Escrow bank
Mashreq Bank
Name in Arabic
إيليت 10 سبورتس ريزيدنس
Project number
1607
Site inspections
7

Schedule

The register lists Elite 10 Sports Residence as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201520162017
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 December 2017

100%+15 pts

  • Elite 10 Sports Residence construction site, inspection photo 1, 25 December 2017
  • Elite 10 Sports Residence construction site, inspection photo 2, 25 December 2017
  • Elite 10 Sports Residence construction site, inspection photo 3, 25 December 2017
  • Elite 10 Sports Residence construction site, inspection photo 4, 25 December 2017

27 July 2017

85%+11 pts

  • Elite 10 Sports Residence construction site, inspection photo 1, 27 July 2017
  • Elite 10 Sports Residence construction site, inspection photo 2, 27 July 2017
  • Elite 10 Sports Residence construction site, inspection photo 3, 27 July 2017
  • Elite 10 Sports Residence construction site, inspection photo 4, 27 July 2017

10 May 2017

74%+9.2 pts

  • Elite 10 Sports Residence construction site, inspection photo 1, 10 May 2017
  • Elite 10 Sports Residence construction site, inspection photo 2, 10 May 2017
  • Elite 10 Sports Residence construction site, inspection photo 3, 10 May 2017
  • Elite 10 Sports Residence construction site, inspection photo 4, 10 May 2017

16 March 2017

65%+36 pts

  • Elite 10 Sports Residence construction site, inspection photo 1, 16 March 2017
  • Elite 10 Sports Residence construction site, inspection photo 2, 16 March 2017
  • Elite 10 Sports Residence construction site, inspection photo 3, 16 March 2017
  • Elite 10 Sports Residence construction site, inspection photo 4, 16 March 2017

6 June 2016

29%+9.0 pts

  • Elite 10 Sports Residence construction site, inspection photo 1, 6 June 2016
  • Elite 10 Sports Residence construction site, inspection photo 2, 6 June 2016
  • Elite 10 Sports Residence construction site, inspection photo 3, 6 June 2016
  • Elite 10 Sports Residence construction site, inspection photo 4, 6 June 2016

28 December 2015

20%+7.3 pts

  • Elite 10 Sports Residence construction site, inspection photo 1, 28 December 2015
  • Elite 10 Sports Residence construction site, inspection photo 2, 28 December 2015
  • Elite 10 Sports Residence construction site, inspection photo 3, 28 December 2015

29 September 2015

13%

  • Elite 10 Sports Residence construction site, inspection photo 1, 29 September 2015

All 44 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 46% built on average.

Own a unit in Elite 10 Sports Residence?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Elite 10 Sports Residence handover date?
Construction of Elite 10 Sports Residence is recorded as complete, with a registered completion date of December 2017. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Elite 10 Sports Residence?
Elite 10 Sports Residence was 100% built at the site inspection on 25 December 2017. The site has been inspected 7 times since September 2015. The Land Department took 44 site photos at its inspections.
Is Elite 10 Sports Residence delayed?
The register lists construction as complete.
Who is building Elite 10 Sports Residence?
The registered developer is Range 4 Developments.
Which bank holds the escrow account for Elite 10 Sports Residence?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.