Elite 10 Sports Residence construction photos

44 photos from 7 site inspections, newest first. The percentage is how much of Elite 10 Sports Residence was built on the day of each visit.

25 December 2017100% built

27 July 201785% built

10 May 201774% built

16 March 201765% built

6 June 201629% built

28 December 201520% built

29 September 201513% built

Back to Elite 10 Sports Residence construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.