Amal Tower construction progress

The register lists Amal Tower in Dubai Sports City as complete, with a registered completion date of January 2025. Its last site inspection on record was in January 2025. The developer is Consolidated Urban Real Estate Development Co.

100%

Built, at the site inspection of 7 January 2025

Construction complete

Registered completion date
January 2025
Construction started
August 2015
First registered
July 2015
Developer
Consolidated Urban Real Estate Development Co
Units
346
Escrow bank
Dubai Islamic Bank
Name in Arabic
برج امل
Project number
591
Site inspections
18

Schedule

The register lists Amal Tower as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20162018202020222024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

7 January 2025

100%+2.0 pts

  • Amal Tower construction site, inspection photo 1, 7 January 2025
  • Amal Tower construction site, inspection photo 2, 7 January 2025
  • Amal Tower construction site, inspection photo 3, 7 January 2025
  • Amal Tower construction site, inspection photo 4, 7 January 2025

18 October 2024

98%+8.0 pts

  • Amal Tower construction site, inspection photo 1, 18 October 2024
  • Amal Tower construction site, inspection photo 2, 18 October 2024
  • Amal Tower construction site, inspection photo 3, 18 October 2024
  • Amal Tower construction site, inspection photo 4, 18 October 2024

12 June 2024

90%+18 pts

  • Amal Tower construction site, inspection photo 1, 12 June 2024
  • Amal Tower construction site, inspection photo 2, 12 June 2024
  • Amal Tower construction site, inspection photo 3, 12 June 2024
  • Amal Tower construction site, inspection photo 4, 12 June 2024

21 February 2024

72%+14 pts

  • Amal Tower construction site, inspection photo 1, 21 February 2024
  • Amal Tower construction site, inspection photo 2, 21 February 2024
  • Amal Tower construction site, inspection photo 3, 21 February 2024
  • Amal Tower construction site, inspection photo 4, 21 February 2024

9 November 2023

58%+4.1 pts

  • Amal Tower construction site, inspection photo 1, 9 November 2023
  • Amal Tower construction site, inspection photo 2, 9 November 2023
  • Amal Tower construction site, inspection photo 3, 9 November 2023
  • Amal Tower construction site, inspection photo 4, 9 November 2023

25 July 2023

54%+17 pts

  • Amal Tower construction site, inspection photo 1, 25 July 2023
  • Amal Tower construction site, inspection photo 2, 25 July 2023
  • Amal Tower construction site, inspection photo 3, 25 July 2023
  • Amal Tower construction site, inspection photo 4, 25 July 2023

27 February 2023

37%+5.7 pts

  • Amal Tower construction site, inspection photo 1, 27 February 2023
  • Amal Tower construction site, inspection photo 2, 27 February 2023
  • Amal Tower construction site, inspection photo 3, 27 February 2023
  • Amal Tower construction site, inspection photo 4, 27 February 2023

12 September 2022

31%+3.1 pts

  • Amal Tower construction site, inspection photo 1, 12 September 2022
  • Amal Tower construction site, inspection photo 2, 12 September 2022
  • Amal Tower construction site, inspection photo 3, 12 September 2022
  • Amal Tower construction site, inspection photo 4, 12 September 2022

10 May 2022

28%+2.6 pts

  • Amal Tower construction site, inspection photo 1, 10 May 2022
  • Amal Tower construction site, inspection photo 2, 10 May 2022
  • Amal Tower construction site, inspection photo 3, 10 May 2022
  • Amal Tower construction site, inspection photo 4, 10 May 2022

2 November 2021

26%+3.7 pts

  • Amal Tower construction site, inspection photo 1, 2 November 2021
  • Amal Tower construction site, inspection photo 2, 2 November 2021
  • Amal Tower construction site, inspection photo 3, 2 November 2021
  • Amal Tower construction site, inspection photo 4, 2 November 2021

All 140 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 46% built on average.

Own a unit in Amal Tower?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Amal Tower handover date?
Construction of Amal Tower is recorded as complete, with a registered completion date of January 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Amal Tower?
Amal Tower was 100% built at the site inspection on 7 January 2025. The site has been inspected 18 times since September 2015. The Land Department took 140 site photos at its inspections.
Is Amal Tower delayed?
The register lists construction as complete.
Who is building Amal Tower?
The registered developer is Consolidated Urban Real Estate Development Co.
Which bank holds the escrow account for Amal Tower?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.