Amal Tower construction photos
140 photos from 18 site inspections, newest first. The percentage is how much of Amal Tower was built on the day of each visit.
7 January 2025100% built
18 October 202498% built
12 June 202490% built
21 February 202472% built
9 November 202358% built
25 July 202354% built
27 February 202337% built
12 September 202231% built
10 May 202228% built
2 November 202126% built
22 September 202022% built
5 March 202020% built
2 May 201920% built
11 December 201814% built
10 October 20187.4% built
8 April 20186.0% built
14 February 20173.8% built
16 September 20153.5% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.



































.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)