The Pulse Villas 2 construction progress

The register lists The Pulse Villas 2 in Dubai South Residential District as complete, with a registered completion date of January 2024. Its last site inspection on record was in February 2024. The developer is Dubai South Properties Dwc.

100%

Built, at the site inspection of 21 February 2024

Construction complete

Registered completion date
January 2024
Construction started
January 2022
First registered
October 2021
Units
74
Escrow bank
Dubai Islamic Bank
Name in Arabic
فلل النبض 2
Project number
2279
Site inspections
5

Schedule

The register lists The Pulse Villas 2 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20232024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 February 2024

100%+13 pts

  • The Pulse Villas 2 construction site, inspection photo 1, 21 February 2024
  • The Pulse Villas 2 construction site, inspection photo 2, 21 February 2024
  • The Pulse Villas 2 construction site, inspection photo 3, 21 February 2024
  • The Pulse Villas 2 construction site, inspection photo 4, 21 February 2024

30 May 2023

87%+15 pts

  • The Pulse Villas 2 construction site, inspection photo 1, 30 May 2023
  • The Pulse Villas 2 construction site, inspection photo 2, 30 May 2023
  • The Pulse Villas 2 construction site, inspection photo 3, 30 May 2023
  • The Pulse Villas 2 construction site, inspection photo 4, 30 May 2023

22 February 2023

72%+41 pts

  • The Pulse Villas 2 construction site, inspection photo 1, 22 February 2023
  • The Pulse Villas 2 construction site, inspection photo 2, 22 February 2023
  • The Pulse Villas 2 construction site, inspection photo 3, 22 February 2023
  • The Pulse Villas 2 construction site, inspection photo 4, 22 February 2023

12 September 2022

30%+19 pts

  • The Pulse Villas 2 construction site, inspection photo 1, 12 September 2022
  • The Pulse Villas 2 construction site, inspection photo 2, 12 September 2022
  • The Pulse Villas 2 construction site, inspection photo 3, 12 September 2022
  • The Pulse Villas 2 construction site, inspection photo 4, 12 September 2022

23 May 2022

11%

  • The Pulse Villas 2 construction site, inspection photo 1, 23 May 2022
  • The Pulse Villas 2 construction site, inspection photo 2, 23 May 2022
  • The Pulse Villas 2 construction site, inspection photo 3, 23 May 2022
  • The Pulse Villas 2 construction site, inspection photo 4, 23 May 2022

All 44 site photos, by inspection date

Context

Dubai South Residential District has 37 projects under construction, 43% built on average.

Dubai South Properties Dwc has 19 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in The Pulse Villas 2?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Pulse Villas 2 handover date?
Construction of The Pulse Villas 2 is recorded as complete, with a registered completion date of January 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Pulse Villas 2?
The Pulse Villas 2 was 100% built at the site inspection on 21 February 2024. The site has been inspected 5 times since May 2022. The Land Department took 44 site photos at its inspections.
Is The Pulse Villas 2 delayed?
The register lists construction as complete.
Who is building The Pulse Villas 2?
The registered developer is Dubai South Properties Dwc. It has 19 other projects under construction in Dubai.
Which bank holds the escrow account for The Pulse Villas 2?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.