The Pulse Residence Plaza construction progress

The register lists The Pulse Residence Plaza in Dubai South Residential District as complete, with a registered completion date of March 2021. Its last site inspection on record was in March 2021. The developer is Dubai South Properties Dwc.

100%

Built, at the site inspection of 15 March 2021

Construction complete

Registered completion date
March 2021
Construction started
July 2017
First registered
March 2017
Units
193
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
مساكن النبض بلازا
Project number
1883
Site inspections
4

Schedule

The register lists The Pulse Residence Plaza as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2018201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 March 2021

100%+37 pts

  • The Pulse Residence Plaza construction site, inspection photo 1, 15 March 2021
  • The Pulse Residence Plaza construction site, inspection photo 2, 15 March 2021
  • The Pulse Residence Plaza construction site, inspection photo 3, 15 March 2021
  • The Pulse Residence Plaza construction site, inspection photo 4, 15 March 2021

26 January 2020

63%+31 pts

  • The Pulse Residence Plaza construction site, inspection photo 1, 26 January 2020
  • The Pulse Residence Plaza construction site, inspection photo 2, 26 January 2020
  • The Pulse Residence Plaza construction site, inspection photo 3, 26 January 2020
  • The Pulse Residence Plaza construction site, inspection photo 4, 26 January 2020

26 June 2019

32%+31 pts

  • The Pulse Residence Plaza construction site, inspection photo 1, 26 June 2019
  • The Pulse Residence Plaza construction site, inspection photo 2, 26 June 2019
  • The Pulse Residence Plaza construction site, inspection photo 3, 26 June 2019
  • The Pulse Residence Plaza construction site, inspection photo 4, 26 June 2019

15 May 2018

1.1%

  • The Pulse Residence Plaza construction site, inspection photo 1, 15 May 2018
  • The Pulse Residence Plaza construction site, inspection photo 2, 15 May 2018
  • The Pulse Residence Plaza construction site, inspection photo 3, 15 May 2018
  • The Pulse Residence Plaza construction site, inspection photo 4, 15 May 2018

All 40 site photos, by inspection date

Context

Dubai South Residential District has 37 projects under construction, 43% built on average.

Dubai South Properties Dwc has 19 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in The Pulse Residence Plaza?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Pulse Residence Plaza handover date?
Construction of The Pulse Residence Plaza is recorded as complete, with a registered completion date of March 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Pulse Residence Plaza?
The Pulse Residence Plaza was 100% built at the site inspection on 15 March 2021. The site has been inspected 4 times since May 2018. The Land Department took 40 site photos at its inspections.
Is The Pulse Residence Plaza delayed?
The register lists construction as complete.
Who is building The Pulse Residence Plaza?
The registered developer is Dubai South Properties Dwc. It has 19 other projects under construction in Dubai.
Which bank holds the escrow account for The Pulse Residence Plaza?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.