South Living construction progress

The register lists South Living in Dubai South Residential District as complete, with a registered completion date of February 2020. Its last site inspection on record was in July 2026. The developer is Dubai South Properties Dwc.

100%

Built, at the site inspection of 28 July 2026

Construction complete

Registered completion date
February 2020
Construction started
January 2018
First registered
August 2017
Units
209
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ساوث ليفينج
Project number
1946
Site inspections
4

Schedule

The register lists South Living as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2019202120232025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 July 2026

89%+24 pts

  • South Living construction site, inspection photo 1, 28 July 2026
  • South Living construction site, inspection photo 2, 28 July 2026
  • South Living construction site, inspection photo 3, 28 July 2026
  • South Living construction site, inspection photo 4, 28 July 2026

12 February 2026

65%+35 pts

  • South Living construction site, inspection photo 1, 12 February 2026
  • South Living construction site, inspection photo 2, 12 February 2026
  • South Living construction site, inspection photo 3, 12 February 2026
  • South Living construction site, inspection photo 4, 12 February 2026

20 August 2025

30%+25 pts

  • South Living construction site, inspection photo 1, 20 August 2025
  • South Living construction site, inspection photo 2, 20 August 2025
  • South Living construction site, inspection photo 3, 20 August 2025
  • South Living construction site, inspection photo 4, 20 August 2025

28 January 2025

4.8%

  • South Living construction site, inspection photo 1, 28 January 2025
  • South Living construction site, inspection photo 2, 28 January 2025
  • South Living construction site, inspection photo 3, 28 January 2025
  • South Living construction site, inspection photo 4, 28 January 2025

All 38 site photos, by inspection date

Context

Dubai South Residential District has 37 projects under construction, 43% built on average.

Dubai South Properties Dwc has 19 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in South Living?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the South Living handover date?
Construction of South Living is recorded as complete, with a registered completion date of February 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on South Living?
South Living was 100% built at the site inspection on 28 July 2026. The site has been inspected 4 times since January 2025. The Land Department took 38 site photos at its inspections.
Is South Living delayed?
The register lists construction as complete.
Who is building South Living?
The registered developer is Dubai South Properties Dwc. It has 19 other projects under construction in Dubai.
Which bank holds the escrow account for South Living?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.