Oceanz 3 By Danube construction progress

Oceanz 3 By Danube in Dubai Maritime City is 21% built at the Land Department inspection of August 2026. Developer Danube Properties Development.

21%

Built, at the Land Department site inspection of 4 August 2026

Finish at recent pace
December 2031
Construction started
May 2024
Registered with the Land Department
January 2024
Units
393
Escrow bank
First Abu Dhabi Bank
Name in Arabic
أوشنز 3 من دانوب
Land Department project number
2867
Land Department site inspections
9

Schedule

Since October 2025 Oceanz 3 By Danube has added about 1.2 points a month. At that rate the site reaches 100% around December 2031. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%202420252026
Progress at each Land Department site inspection

Site inspections

4 August 2026

21%+4.6 pts

  • Oceanz 3 By Danube construction site, Land Department inspection photo 1, 4 August 2026
  • Oceanz 3 By Danube construction site, Land Department inspection photo 2, 4 August 2026
  • Oceanz 3 By Danube construction site, Land Department inspection photo 3, 4 August 2026
  • Oceanz 3 By Danube construction site, Land Department inspection photo 4, 4 August 2026

27 April 2026

16%+3.0 pts

  • Oceanz 3 By Danube construction site, Land Department inspection photo 1, 27 April 2026
  • Oceanz 3 By Danube construction site, Land Department inspection photo 2, 27 April 2026
  • Oceanz 3 By Danube construction site, Land Department inspection photo 3, 27 April 2026
  • Oceanz 3 By Danube construction site, Land Department inspection photo 4, 27 April 2026

14 January 2026

13%+3.8 pts

  • Oceanz 3 By Danube construction site, Land Department inspection photo 1, 14 January 2026
  • Oceanz 3 By Danube construction site, Land Department inspection photo 2, 14 January 2026
  • Oceanz 3 By Danube construction site, Land Department inspection photo 3, 14 January 2026

28 October 2025

9.3%+2.0 pts

  • Oceanz 3 By Danube construction site, Land Department inspection photo 1, 28 October 2025
  • Oceanz 3 By Danube construction site, Land Department inspection photo 2, 28 October 2025
  • Oceanz 3 By Danube construction site, Land Department inspection photo 3, 28 October 2025

3 July 2025

7.2%+1.8 pts

  • Oceanz 3 By Danube construction site, Land Department inspection photo 1, 3 July 2025
  • Oceanz 3 By Danube construction site, Land Department inspection photo 2, 3 July 2025
  • Oceanz 3 By Danube construction site, Land Department inspection photo 3, 3 July 2025
  • Oceanz 3 By Danube construction site, Land Department inspection photo 4, 3 July 2025

28 January 2025

5.5%+1.4 pts

  • Oceanz 3 By Danube construction site, Land Department inspection photo 1, 28 January 2025
  • Oceanz 3 By Danube construction site, Land Department inspection photo 2, 28 January 2025
  • Oceanz 3 By Danube construction site, Land Department inspection photo 3, 28 January 2025

16 December 2024

4.0%+3.2 pts

  • Oceanz 3 By Danube construction site, Land Department inspection photo 1, 16 December 2024
  • Oceanz 3 By Danube construction site, Land Department inspection photo 2, 16 December 2024
  • Oceanz 3 By Danube construction site, Land Department inspection photo 3, 16 December 2024
  • Oceanz 3 By Danube construction site, Land Department inspection photo 4, 16 December 2024

23 April 2024

0.8%+0.8 pts

  • Oceanz 3 By Danube construction site, Land Department inspection photo 1, 23 April 2024
  • Oceanz 3 By Danube construction site, Land Department inspection photo 2, 23 April 2024
  • Oceanz 3 By Danube construction site, Land Department inspection photo 3, 23 April 2024
  • Oceanz 3 By Danube construction site, Land Department inspection photo 4, 23 April 2024

7 December 2023

0%

  • Oceanz 3 By Danube construction site, Land Department inspection photo 1, 7 December 2023
  • Oceanz 3 By Danube construction site, Land Department inspection photo 2, 7 December 2023

All 37 site photos, by inspection date

Context

Dubai Maritime City has 23 projects under construction, 29% built on average.

Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Oceanz 3 By Danube?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Oceanz 3 By Danube be completed?
The Land Department has no completion date on record for Oceanz 3 By Danube yet.
How much of Oceanz 3 By Danube is built?
21%, measured at the Land Department site inspection on 4 August 2026. The Land Department engineers have inspected the site 9 times since December 2023.
Who is building Oceanz 3 By Danube?
The registered developer is Danube Properties Development. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Oceanz 3 By Danube?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.