Oceanz 3 By Danube construction progress

No completion date is registered for Oceanz 3 By Danube in Dubai Maritime City yet. At the last site inspection, in November 2026, it was 27% built. The developer is Danube Properties Development.

27%

Built, at the site inspection of 17 November 2026

Finish at recent pace
May 2031
Construction started
May 2024
First registered
January 2024
Units
393
Escrow bank
First Abu Dhabi Bank
Name in Arabic
أوشنز 3 من دانوب
Project number
2867
Site inspections
10

Schedule

Since January 2026 Oceanz 3 By Danube has added about 1.4 points a month. At that rate the site reaches 100% around May 2031. No completion date is on record to compare it with.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

17 November 2026

27%+6.1 pts

  • Oceanz 3 By Danube construction site, inspection photo 1, 17 November 2026
  • Oceanz 3 By Danube construction site, inspection photo 2, 17 November 2026
  • Oceanz 3 By Danube construction site, inspection photo 3, 17 November 2026
  • Oceanz 3 By Danube construction site, inspection photo 4, 17 November 2026

4 August 2026

21%+4.6 pts

  • Oceanz 3 By Danube construction site, inspection photo 1, 4 August 2026
  • Oceanz 3 By Danube construction site, inspection photo 2, 4 August 2026
  • Oceanz 3 By Danube construction site, inspection photo 3, 4 August 2026
  • Oceanz 3 By Danube construction site, inspection photo 4, 4 August 2026

27 April 2026

16%+3.0 pts

  • Oceanz 3 By Danube construction site, inspection photo 1, 27 April 2026
  • Oceanz 3 By Danube construction site, inspection photo 2, 27 April 2026
  • Oceanz 3 By Danube construction site, inspection photo 3, 27 April 2026
  • Oceanz 3 By Danube construction site, inspection photo 4, 27 April 2026

14 January 2026

13%+3.8 pts

  • Oceanz 3 By Danube construction site, inspection photo 1, 14 January 2026
  • Oceanz 3 By Danube construction site, inspection photo 2, 14 January 2026
  • Oceanz 3 By Danube construction site, inspection photo 3, 14 January 2026

28 October 2025

9.3%+2.0 pts

  • Oceanz 3 By Danube construction site, inspection photo 1, 28 October 2025
  • Oceanz 3 By Danube construction site, inspection photo 2, 28 October 2025
  • Oceanz 3 By Danube construction site, inspection photo 3, 28 October 2025

3 July 2025

7.2%+1.8 pts

  • Oceanz 3 By Danube construction site, inspection photo 1, 3 July 2025
  • Oceanz 3 By Danube construction site, inspection photo 2, 3 July 2025
  • Oceanz 3 By Danube construction site, inspection photo 3, 3 July 2025
  • Oceanz 3 By Danube construction site, inspection photo 4, 3 July 2025

28 January 2025

5.5%+1.4 pts

  • Oceanz 3 By Danube construction site, inspection photo 1, 28 January 2025
  • Oceanz 3 By Danube construction site, inspection photo 2, 28 January 2025
  • Oceanz 3 By Danube construction site, inspection photo 3, 28 January 2025

16 December 2024

4.0%+3.2 pts

  • Oceanz 3 By Danube construction site, inspection photo 1, 16 December 2024
  • Oceanz 3 By Danube construction site, inspection photo 2, 16 December 2024
  • Oceanz 3 By Danube construction site, inspection photo 3, 16 December 2024
  • Oceanz 3 By Danube construction site, inspection photo 4, 16 December 2024

23 April 2024

0.8%+0.8 pts

  • Oceanz 3 By Danube construction site, inspection photo 1, 23 April 2024
  • Oceanz 3 By Danube construction site, inspection photo 2, 23 April 2024
  • Oceanz 3 By Danube construction site, inspection photo 3, 23 April 2024
  • Oceanz 3 By Danube construction site, inspection photo 4, 23 April 2024

7 December 2023

0%

  • Oceanz 3 By Danube construction site, inspection photo 1, 7 December 2023
  • Oceanz 3 By Danube construction site, inspection photo 2, 7 December 2023

All 44 site photos, by inspection date

Context

Dubai Maritime City has 23 projects under construction, 32% built on average.

Danube Properties Development has 23 projects under construction in Dubai; 4 have passed their registered completion date.

Own a unit in Oceanz 3 By Danube?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Oceanz 3 By Danube handover date?
No completion date is on record for Oceanz 3 By Danube yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Oceanz 3 By Danube?
Oceanz 3 By Danube was 27% built at the site inspection on 17 November 2026. The site has been inspected 10 times since December 2023. The Land Department took 44 site photos at its inspections.
Who is building Oceanz 3 By Danube?
The registered developer is Danube Properties Development. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Oceanz 3 By Danube?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.