44 photos from 10 site inspections, newest first. The percentage is how much of Oceanz 3 By Danube was built on the day of each visit.

17 November 202627% built

4 August 202621% built

27 April 202616% built

14 January 202613% built

28 October 20259.3% built

3 July 20257.2% built

28 January 20255.5% built

16 December 20244.0% built

23 April 20240.8% built

7 December 20230% built

Back to Oceanz 3 By Danube construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.