Nautica Two construction photos
60 photos from 9 site inspections, newest first. The percentage is how much of Nautica Two was built on the day of each visit.
3 September 202685% built
24 April 202664% built
4 December 202546% built
27 August 202532% built
25 June 202527% built
24 February 202515% built
28 October 20247.4% built
1 May 20241.1% built
19 September 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.