Nautica One construction photos
62 photos from 9 site inspections, newest first. The percentage is how much of Nautica One was built on the day of each visit.
3 September 202685% built
24 April 202665% built
4 December 202547% built
27 August 202532% built
25 June 202524% built
27 February 202518% built
28 October 20247.3% built
1 May 20240.9% built
19 September 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.