Liv Residence construction progress

The register lists Liv Residence in Dubai Marina as complete, with a registered completion date of April 2020. Its last site inspection on record was in March 2020. The developer is L I V Real Estate Development.

100%

Built, at the site inspection of 16 March 2020

Construction complete

Registered completion date
April 2020
Construction started
September 2016
First registered
May 2017
Developer
L I V Real Estate Development
Community
Dubai Marina
Units
190
Escrow bank
Dubai Islamic Bank
Name in Arabic
ليف رسيدنس
Project number
1827
Site inspections
9

Schedule

The register lists Liv Residence as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2017201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 March 2020

100%+1.3 pts

  • Liv Residence construction site, inspection photo 1, 16 March 2020
  • Liv Residence construction site, inspection photo 2, 16 March 2020
  • Liv Residence construction site, inspection photo 3, 16 March 2020
  • Liv Residence construction site, inspection photo 4, 16 March 2020

30 January 2020

99%+6.4 pts

  • Liv Residence construction site, inspection photo 1, 30 January 2020
  • Liv Residence construction site, inspection photo 2, 30 January 2020
  • Liv Residence construction site, inspection photo 3, 30 January 2020
  • Liv Residence construction site, inspection photo 4, 30 January 2020

28 October 2019

92%+7.3 pts

  • Liv Residence construction site, inspection photo 1, 28 October 2019
  • Liv Residence construction site, inspection photo 2, 28 October 2019
  • Liv Residence construction site, inspection photo 3, 28 October 2019
  • Liv Residence construction site, inspection photo 4, 28 October 2019

23 June 2019

85%+15 pts

  • Liv Residence construction site, inspection photo 1, 23 June 2019
  • Liv Residence construction site, inspection photo 2, 23 June 2019
  • Liv Residence construction site, inspection photo 3, 23 June 2019
  • Liv Residence construction site, inspection photo 4, 23 June 2019

27 March 2019

70%+20 pts

  • Liv Residence construction site, inspection photo 1, 27 March 2019
  • Liv Residence construction site, inspection photo 2, 27 March 2019
  • Liv Residence construction site, inspection photo 3, 27 March 2019
  • Liv Residence construction site, inspection photo 4, 27 March 2019

5 November 2018

50%+16 pts

  • Liv Residence construction site, inspection photo 1, 5 November 2018
  • Liv Residence construction site, inspection photo 2, 5 November 2018
  • Liv Residence construction site, inspection photo 3, 5 November 2018
  • Liv Residence construction site, inspection photo 4, 5 November 2018

27 June 2018

34%+14 pts

  • Liv Residence construction site, inspection photo 1, 27 June 2018
  • Liv Residence construction site, inspection photo 2, 27 June 2018
  • Liv Residence construction site, inspection photo 3, 27 June 2018
  • Liv Residence construction site, inspection photo 4, 27 June 2018

6 March 2018

20%+7.1 pts

  • Liv Residence construction site, inspection photo 1, 6 March 2018
  • Liv Residence construction site, inspection photo 2, 6 March 2018
  • Liv Residence construction site, inspection photo 3, 6 March 2018
  • Liv Residence construction site, inspection photo 4, 6 March 2018

22 November 2017

13%

  • Liv Residence construction site, inspection photo 1, 22 November 2017
  • Liv Residence construction site, inspection photo 2, 22 November 2017
  • Liv Residence construction site, inspection photo 3, 22 November 2017
  • Liv Residence construction site, inspection photo 4, 22 November 2017

All 91 site photos, by inspection date

Context

Dubai Marina has 13 projects under construction, 46% built on average.

Own a unit in Liv Residence?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Liv Residence handover date?
Construction of Liv Residence is recorded as complete, with a registered completion date of April 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Liv Residence?
Liv Residence was 100% built at the site inspection on 16 March 2020. The site has been inspected 9 times since November 2017. The Land Department took 91 site photos at its inspections.
Is Liv Residence delayed?
The register lists construction as complete.
Who is building Liv Residence?
The registered developer is L I V Real Estate Development.
Which bank holds the escrow account for Liv Residence?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.