Liv Residence construction photos

91 photos from 9 site inspections, newest first. The percentage is how much of Liv Residence was built on the day of each visit.

16 March 2020100% built

30 January 202099% built

28 October 201992% built

23 June 201985% built

27 March 201970% built

5 November 201850% built

27 June 201834% built

6 March 201820% built

22 November 201713% built

Back to Liv Residence construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.