Liv Lux construction photos

69 photos taken by Dubai Land Department engineers at 10 site inspections, newest first. The percentage is how much of Liv Lux was built on the day of each visit.

2 June 202679% built

12 January 202669% built

17 September 202552% built

14 May 202541% built

7 February 202535% built

14 October 202421% built

2 July 202416% built

13 March 202411% built

25 August 20233.1% built

8 November 20220% built

Back to Liv Lux construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.