Peace Lagoons Ii By Peace Homes construction progress
Peace Lagoons Ii By Peace Homes in Dubai Land Residence Complex is 4.0% built at the Land Department inspection of April 2026. Developer Peace Homes Development. Completion registered for January 2029.
4.0%
Built, at the Land Department site inspection of 23 April 2026
Running behind its date
- Completion date (Land Department)
- January 2029
- Finish at recent pace
- March 2042
- Construction started
- January 2025
- Registered with the Land Department
- March 2025
- Developer
- Peace Homes Development
- Community
- Dubai Land Residence Complex
- Units
- 831
- Escrow bank
- Bank of Sharjah
- Name in Arabic
- بيس لاغونز 2 باي بيس هومز
- Land Department project number
- 3383
- Land Department site inspections
- 2
Schedule
Between October 2025 and April 2026 the site added about 0.5 points a month. At that rate it would finish around March 2042, more than three months after the January 2029 date registered with the Land Department.
Site inspections
23 April 2026
4.0%+3.0 pts
23 October 2025
1.0%
Context
Dubai Land Residence Complex has 65 projects under construction, 24% built on average.
Peace Homes Development has 5 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Peace Lagoons Ii By Peace Homes?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Peace Lagoons Ii By Peace Homes be completed?
- The completion date registered with the Dubai Land Department is January 2029. At the pace of its recent inspections the site would reach 100% around March 2042. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Peace Lagoons Ii By Peace Homes is built?
- 4.0%, measured at the Land Department site inspection on 23 April 2026. The Land Department engineers have inspected the site 2 times since October 2025.
- Is Peace Lagoons Ii By Peace Homes delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2029.
- Who is building Peace Lagoons Ii By Peace Homes?
- The registered developer is Peace Homes Development. It has 4 other projects under construction in Dubai.
- Which bank holds the escrow account for Peace Lagoons Ii By Peace Homes?
- Bank of Sharjah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sky Vista By Peace HomesAlso by Peace Homes Development. 61%.
- Sky Livings By Peace HomesAlso by Peace Homes Development. 60%.
- Peace Lagoons By Peace HomesAlso by Peace Homes Development. 2.9%, Due September 2028.
- Peace Avenue By Peace HomesAlso by Peace Homes Development. 3.5%, Due January 2029.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026.
- Ag SquareNearby in Dubai Land Residence Complex. 69%.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.