Peace Lagoons By Peace Homes construction progress

The registered completion date for Peace Lagoons By Peace Homes in Dubai Land Residence Complex is September 2028. At the last site inspection, in October 2026, it was 4.2% built. The developer is Peace Homes Development.

4.2%

Built, at the site inspection of 21 October 2026

Running behind its date

Registered completion date
September 2028
Finish at recent pace
June 2064
Construction started
September 2024
First registered
June 2024
Units
1,000
Escrow bank
Bank of Sharjah
Name in Arabic
بيس لاغونز باي بيس هومز
Project number
3146
Site inspections
4

Schedule

Between April 2026 and October 2026 the site added about 0.2 points a month. At that rate it would finish around June 2064, more than three months after its registered date of September 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 October 2026

4.2%+1.3 pts

  • Peace Lagoons By Peace Homes construction site, inspection photo 1, 21 October 2026
  • Peace Lagoons By Peace Homes construction site, inspection photo 2, 21 October 2026
  • Peace Lagoons By Peace Homes construction site, inspection photo 3, 21 October 2026
  • Peace Lagoons By Peace Homes construction site, inspection photo 4, 21 October 2026

23 April 2026

2.9%+2.6 pts

  • Peace Lagoons By Peace Homes construction site, inspection photo 1, 23 April 2026
  • Peace Lagoons By Peace Homes construction site, inspection photo 2, 23 April 2026
  • Peace Lagoons By Peace Homes construction site, inspection photo 3, 23 April 2026
  • Peace Lagoons By Peace Homes construction site, inspection photo 4, 23 April 2026

19 March 2025

0.3%+0.3 pts

  • Peace Lagoons By Peace Homes construction site, inspection photo 1, 19 March 2025
  • Peace Lagoons By Peace Homes construction site, inspection photo 2, 19 March 2025
  • Peace Lagoons By Peace Homes construction site, inspection photo 3, 19 March 2025
  • Peace Lagoons By Peace Homes construction site, inspection photo 4, 19 March 2025

12 June 2024

0%

  • Peace Lagoons By Peace Homes construction site, inspection photo 1, 12 June 2024
  • Peace Lagoons By Peace Homes construction site, inspection photo 2, 12 June 2024
  • Peace Lagoons By Peace Homes construction site, inspection photo 3, 12 June 2024
  • Peace Lagoons By Peace Homes construction site, inspection photo 4, 12 June 2024

All 18 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Peace Homes Development has 5 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Peace Lagoons By Peace Homes?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Peace Lagoons By Peace Homes handover date?
The registered completion date is September 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2064. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Peace Lagoons By Peace Homes?
Peace Lagoons By Peace Homes was 4.2% built at the site inspection on 21 October 2026. The site has been inspected 4 times since June 2024. The Land Department took 18 site photos at its inspections.
Is Peace Lagoons By Peace Homes delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
Who is building Peace Lagoons By Peace Homes?
The registered developer is Peace Homes Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Peace Lagoons By Peace Homes?
Bank of Sharjah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.