Peace Avenue By Peace Homes construction progress

The registered completion date for Peace Avenue By Peace Homes is January 2029. At the last site inspection, in September 2026, it was 3.5% built. The developer is Peace Homes Development.

3.5%

Built, at the site inspection of 3 September 2026

Running behind its date

Registered completion date
January 2029
Finish at recent pace
December 2050
Construction started
January 2026
First registered
January 2026
Units
266
Escrow bank
Bank of Sharjah
Name in Arabic
بيس أفينيو باي بيس هومز
Project number
4146
Site inspections
2

Schedule

Between October 2025 and September 2026 the site added about 0.3 points a month. At that rate it would finish around December 2050, more than three months after its registered date of January 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 September 2026

3.5%+3.5 pts

  • Peace Avenue By Peace Homes construction site, inspection photo 1, 3 September 2026
  • Peace Avenue By Peace Homes construction site, inspection photo 2, 3 September 2026
  • Peace Avenue By Peace Homes construction site, inspection photo 3, 3 September 2026
  • Peace Avenue By Peace Homes construction site, inspection photo 4, 3 September 2026

14 October 2025

0%

  • Peace Avenue By Peace Homes construction site, inspection photo 1, 14 October 2025
  • Peace Avenue By Peace Homes construction site, inspection photo 2, 14 October 2025

All 6 site photos, by inspection date

Context

Peace Homes Development has 5 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Peace Avenue By Peace Homes?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Peace Avenue By Peace Homes handover date?
The registered completion date is January 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2050. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Peace Avenue By Peace Homes?
Peace Avenue By Peace Homes was 3.5% built at the site inspection on 3 September 2026. The site has been inspected 2 times since October 2025. The Land Department took 6 site photos at its inspections.
Is Peace Avenue By Peace Homes delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2029.
Who is building Peace Avenue By Peace Homes?
The registered developer is Peace Homes Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Peace Avenue By Peace Homes?
Bank of Sharjah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.