Peace Avenue By Peace Homes construction progress

Peace Avenue By Peace Homes is 3.5% built at the Land Department inspection of September 2026. Developer Peace Homes Development. Completion registered for January 2029.

3.5%

Built, at the Land Department site inspection of 3 September 2026

Running behind its date

Completion date (Land Department)
January 2029
Finish at recent pace
December 2050
Construction started
January 2026
Registered with the Land Department
January 2026
Units
266
Escrow bank
Bank of Sharjah
Name in Arabic
بيس أفينيو باي بيس هومز
Land Department project number
4146
Land Department site inspections
2

Schedule

Between October 2025 and September 2026 the site added about 0.3 points a month. At that rate it would finish around December 2050, more than three months after the January 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

3 September 2026

3.5%+3.5 pts

  • Peace Avenue By Peace Homes construction site, Land Department inspection photo 1, 3 September 2026
  • Peace Avenue By Peace Homes construction site, Land Department inspection photo 2, 3 September 2026
  • Peace Avenue By Peace Homes construction site, Land Department inspection photo 3, 3 September 2026
  • Peace Avenue By Peace Homes construction site, Land Department inspection photo 4, 3 September 2026

14 October 2025

0%

  • Peace Avenue By Peace Homes construction site, Land Department inspection photo 1, 14 October 2025
  • Peace Avenue By Peace Homes construction site, Land Department inspection photo 2, 14 October 2025

All 6 site photos, by inspection date

Context

Peace Homes Development has 5 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Peace Avenue By Peace Homes?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Peace Avenue By Peace Homes be completed?
The completion date registered with the Dubai Land Department is January 2029. At the pace of its recent inspections the site would reach 100% around December 2050. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Peace Avenue By Peace Homes is built?
3.5%, measured at the Land Department site inspection on 3 September 2026. The Land Department engineers have inspected the site 2 times since October 2025.
Is Peace Avenue By Peace Homes delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2029.
Who is building Peace Avenue By Peace Homes?
The registered developer is Peace Homes Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Peace Avenue By Peace Homes?
Bank of Sharjah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.