Cove Edition Residence 6 By Imtiaz construction progress
Cove Edition Residence 6 By Imtiaz in Dubai Land Residence Complex is 20% built at the Land Department inspection of July 2026. Developer Imtiaz Cove Real Estate Development. Completion registered for September 2027.
20%
Built, at the Land Department site inspection of 13 July 2026
Running behind its date
- Completion date (Land Department)
- September 2027
- Finish at recent pace
- August 2029
- Construction started
- June 2025
- Registered with the Land Department
- June 2025
- Developer
- Imtiaz Cove Real Estate Development
- Community
- Dubai Land Residence Complex
- Units
- 264
- Escrow bank
- Ajman Bank
- Name in Arabic
- كوف ايديشن ريزيدنس 6 من امتياز
- Land Department project number
- 3803
- Land Department site inspections
- 5
Schedule
Between October 2025 and July 2026 the site added about 2.2 points a month. At that rate it would finish around August 2029, more than three months after the September 2027 date registered with the Land Department.
Site inspections
13 July 2026
20%+14 pts
8 April 2026
6.3%+2.1 pts
5 February 2026
4.2%+3.2 pts
20 October 2025
1.1%+1.1 pts
2 June 2025
0%
Context
Dubai Land Residence Complex has 65 projects under construction, 24% built on average.
Imtiaz Cove Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Cove Edition Residence 6 By Imtiaz?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Cove Edition Residence 6 By Imtiaz be completed?
- The completion date registered with the Dubai Land Department is September 2027. At the pace of its recent inspections the site would reach 100% around August 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Cove Edition Residence 6 By Imtiaz is built?
- 20%, measured at the Land Department site inspection on 13 July 2026. The Land Department engineers have inspected the site 5 times since June 2025.
- Is Cove Edition Residence 6 By Imtiaz delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
- Who is building Cove Edition Residence 6 By Imtiaz?
- The registered developer is Imtiaz Cove Real Estate Development. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Cove Edition Residence 6 By Imtiaz?
- Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Cove Grand Residence By ImtiazAlso by Imtiaz Cove Real Estate Development. 13%.
- Le Blanc Residence By ImtiazAlso by Imtiaz Cove Real Estate Development. 6.0%, Due October 2028.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026.
- Ag SquareNearby in Dubai Land Residence Complex. 69%.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)




