Cove Edition Residence 6 By Imtiaz construction progress

The registered completion date for Cove Edition Residence 6 By Imtiaz in Dubai Land Residence Complex is September 2027. At the last site inspection, in October 2026, it was 26% built. The developer is Imtiaz Cove Real Estate Development.

26%

Built, at the site inspection of 13 October 2026

Running behind its date

Registered completion date
September 2027
Finish at recent pace
September 2029
Construction started
June 2025
First registered
June 2025
Units
264
Escrow bank
Ajman Bank
Name in Arabic
كوف ايديشن ريزيدنس 6 من امتياز
Project number
3803
Site inspections
6

Schedule

Between October 2025 and October 2026 the site added about 2.1 points a month. At that rate it would finish around September 2029, more than three months after its registered date of September 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 October 2026

26%+5.8 pts

  • Cove Edition Residence 6 By Imtiaz construction site, inspection photo 1, 13 October 2026
  • Cove Edition Residence 6 By Imtiaz construction site, inspection photo 2, 13 October 2026
  • Cove Edition Residence 6 By Imtiaz construction site, inspection photo 3, 13 October 2026
  • Cove Edition Residence 6 By Imtiaz construction site, inspection photo 4, 13 October 2026

13 July 2026

20%+14 pts

  • Cove Edition Residence 6 By Imtiaz construction site, inspection photo 1, 13 July 2026
  • Cove Edition Residence 6 By Imtiaz construction site, inspection photo 2, 13 July 2026
  • Cove Edition Residence 6 By Imtiaz construction site, inspection photo 3, 13 July 2026
  • Cove Edition Residence 6 By Imtiaz construction site, inspection photo 4, 13 July 2026

8 April 2026

6.3%+2.1 pts

  • Cove Edition Residence 6 By Imtiaz construction site, inspection photo 1, 8 April 2026
  • Cove Edition Residence 6 By Imtiaz construction site, inspection photo 2, 8 April 2026
  • Cove Edition Residence 6 By Imtiaz construction site, inspection photo 3, 8 April 2026
  • Cove Edition Residence 6 By Imtiaz construction site, inspection photo 4, 8 April 2026

5 February 2026

4.2%+3.2 pts

  • Cove Edition Residence 6 By Imtiaz construction site, inspection photo 1, 5 February 2026
  • Cove Edition Residence 6 By Imtiaz construction site, inspection photo 2, 5 February 2026
  • Cove Edition Residence 6 By Imtiaz construction site, inspection photo 3, 5 February 2026
  • Cove Edition Residence 6 By Imtiaz construction site, inspection photo 4, 5 February 2026

20 October 2025

1.1%+1.1 pts

  • Cove Edition Residence 6 By Imtiaz construction site, inspection photo 1, 20 October 2025
  • Cove Edition Residence 6 By Imtiaz construction site, inspection photo 2, 20 October 2025
  • Cove Edition Residence 6 By Imtiaz construction site, inspection photo 3, 20 October 2025

2 June 2025

0%

  • Cove Edition Residence 6 By Imtiaz construction site, inspection photo 1, 2 June 2025
  • Cove Edition Residence 6 By Imtiaz construction site, inspection photo 2, 2 June 2025

All 29 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Imtiaz Cove Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Cove Edition Residence 6 By Imtiaz?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Cove Edition Residence 6 By Imtiaz handover date?
The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Cove Edition Residence 6 By Imtiaz?
Cove Edition Residence 6 By Imtiaz was 26% built at the site inspection on 13 October 2026. The site has been inspected 6 times since June 2025. The Land Department took 29 site photos at its inspections.
Is Cove Edition Residence 6 By Imtiaz delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building Cove Edition Residence 6 By Imtiaz?
The registered developer is Imtiaz Cove Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Cove Edition Residence 6 By Imtiaz?
Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.