Le Blanc Residence By Imtiaz construction progress
The registered completion date for Le Blanc Residence By Imtiaz is October 2028. At the last site inspection, in October 2026, it was 6.0% built. The developer is Imtiaz Cove Real Estate Development.
6.0%
Built, at the site inspection of 8 October 2026
Running behind its date
- Registered completion date
- October 2028
- Finish at recent pace
- November 2041
- Construction started
- January 2026
- First registered
- December 2025
- Developer
- Imtiaz Cove Real Estate Development
- Units
- 323
- Escrow bank
- Ajman Bank
- Name in Arabic
- لي بلانك ريزيدنس من امتياز
- Project number
- 4174
- Site inspections
- 4
Schedule
Between October 2025 and October 2026 the site added about 0.5 points a month. At that rate it would finish around November 2041, more than three months after its registered date of October 2028.
Site inspections
8 October 2026
6.0%+2.5 pts
7 July 2026
3.4%+3.0 pts
8 April 2026
0.4%+0.4 pts
23 October 2025
0%
Context
Imtiaz Cove Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Le Blanc Residence By Imtiaz?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Le Blanc Residence By Imtiaz handover date?
- The registered completion date is October 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2041. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Le Blanc Residence By Imtiaz?
- Le Blanc Residence By Imtiaz was 6.0% built at the site inspection on 8 October 2026. The site has been inspected 4 times since October 2025. The Land Department took 14 site photos at its inspections.
- Is Le Blanc Residence By Imtiaz delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2028.
- Who is building Le Blanc Residence By Imtiaz?
- The registered developer is Imtiaz Cove Real Estate Development. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Le Blanc Residence By Imtiaz?
- Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Cove Grand Residence By ImtiazAlso by Imtiaz Cove Real Estate Development. 13%, Due December 2027.
- Cove Edition Residence 6 By ImtiazAlso by Imtiaz Cove Real Estate Development. 26%, Due September 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)