Celesto Tower construction progress

Celesto Tower in Dubai Land Residence Complex is 3.9% built at the Land Department inspection of June 2026. Developer Tarrad Development. Completion registered for December 2027.

3.9%

Built, at the Land Department site inspection of 18 June 2026

Running behind its date

Completion date (Land Department)
December 2027
Finish at recent pace
July 2044
Construction started
November 2025
Registered with the Land Department
October 2025
Units
271
Escrow bank
Mashreq Bank
Name in Arabic
سيليستو تاور
Land Department project number
4106
Land Department site inspections
3

Schedule

Between September 2025 and June 2026 the site added about 0.4 points a month. At that rate it would finish around July 2044, more than three months after the December 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

18 June 2026

3.9%+1.9 pts

  • Celesto Tower construction site, Land Department inspection photo 1, 18 June 2026
  • Celesto Tower construction site, Land Department inspection photo 2, 18 June 2026
  • Celesto Tower construction site, Land Department inspection photo 3, 18 June 2026
  • Celesto Tower construction site, Land Department inspection photo 4, 18 June 2026

23 March 2026

2.0%+2.0 pts

  • Celesto Tower construction site, Land Department inspection photo 1, 23 March 2026
  • Celesto Tower construction site, Land Department inspection photo 2, 23 March 2026
  • Celesto Tower construction site, Land Department inspection photo 3, 23 March 2026
  • Celesto Tower construction site, Land Department inspection photo 4, 23 March 2026

24 September 2025

0%

  • Celesto Tower construction site, Land Department inspection photo 1, 24 September 2025
  • Celesto Tower construction site, Land Department inspection photo 2, 24 September 2025

All 10 site photos, by inspection date

Context

Dubai Land Residence Complex has 65 projects under construction, 24% built on average.

Tarrad Development has 4 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Celesto Tower?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Celesto Tower be completed?
The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around July 2044. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Celesto Tower is built?
3.9%, measured at the Land Department site inspection on 18 June 2026. The Land Department engineers have inspected the site 3 times since September 2025.
Is Celesto Tower delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Celesto Tower?
The registered developer is Tarrad Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Celesto Tower?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.