Mackerel Tower construction progress
Mackerel Tower in Palm Deira was registered to complete in April 2026 and is still under construction. At the last site inspection, in October 2026, it was 57% built. The developer is Tarrad Development.
57%
Built, at the site inspection of 20 October 2026
8 months past its registered completion date
- Registered completion date
- April 2026
- Finish at recent pace
- December 2027
- Construction started
- November 2024
- First registered
- November 2024
- Developer
- Tarrad Development
- Community
- Palm Deira
- Units
- 62
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- برج ماكريل
- Project number
- 3351
- Site inspections
- 7
Schedule
Mackerel Tower was registered to complete in April 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 3.1 points a month. Kept at that rate, the site would reach 100% around December 2027.
Site inspections
20 October 2026
57%+11 pts
20 July 2026
46%+10 pts
1 April 2026
35%+9.9 pts
15 December 2025
25%+16 pts
16 July 2025
9.3%+2.9 pts
22 March 2025
6.5%+6.5 pts
31 October 2024
0%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Tarrad Development has 4 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Mackerel Tower?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Mackerel Tower handover date?
- The registered completion date was April 2026, and the register still lists Mackerel Tower as under construction. At the pace of its recent inspections the site would reach 100% around December 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Mackerel Tower?
- Mackerel Tower was 57% built at the site inspection on 20 October 2026. The site has been inspected 7 times since October 2024. The Land Department took 49 site photos at its inspections.
- Is Mackerel Tower delayed?
- Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
- Who is building Mackerel Tower?
- The registered developer is Tarrad Development. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Mackerel Tower?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Celesto TowerAlso by Tarrad Development. 3.9%, Due December 2027.
- Celesto Tower 2Also by Tarrad Development. 0%, Due June 2028.
- Celesto Tower 3Also by Tarrad Development. 0%, Due September 2028.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.








.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)