Mackerel Tower construction progress

Mackerel Tower in Palm Deira is 46% built at the Land Department inspection of July 2026. Developer Tarrad Development. Completion registered for April 2026.

46%

Built, at the Land Department site inspection of 20 July 2026

6 months past its registered completion date

Completion date (Land Department)
April 2026
Finish at recent pace
February 2028
Construction started
November 2024
Registered with the Land Department
November 2024
Community
Palm Deira
Units
62
Escrow bank
First Abu Dhabi Bank
Name in Arabic
برج ماكريل
Land Department project number
3351
Land Department site inspections
6

Schedule

Mackerel Tower was registered to complete in April 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 2.9 points a month. Kept at that rate, the site would reach 100% around February 2028.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

20 July 2026

46%+10 pts

  • Mackerel Tower construction site, Land Department inspection photo 1, 20 July 2026
  • Mackerel Tower construction site, Land Department inspection photo 2, 20 July 2026
  • Mackerel Tower construction site, Land Department inspection photo 3, 20 July 2026
  • Mackerel Tower construction site, Land Department inspection photo 4, 20 July 2026

1 April 2026

35%+9.9 pts

  • Mackerel Tower construction site, Land Department inspection photo 1, 1 April 2026
  • Mackerel Tower construction site, Land Department inspection photo 2, 1 April 2026
  • Mackerel Tower construction site, Land Department inspection photo 3, 1 April 2026
  • Mackerel Tower construction site, Land Department inspection photo 4, 1 April 2026

15 December 2025

25%+16 pts

  • Mackerel Tower construction site, Land Department inspection photo 1, 15 December 2025
  • Mackerel Tower construction site, Land Department inspection photo 2, 15 December 2025
  • Mackerel Tower construction site, Land Department inspection photo 3, 15 December 2025
  • Mackerel Tower construction site, Land Department inspection photo 4, 15 December 2025

16 July 2025

9.3%+2.9 pts

  • Mackerel Tower construction site, Land Department inspection photo 1, 16 July 2025
  • Mackerel Tower construction site, Land Department inspection photo 2, 16 July 2025
  • Mackerel Tower construction site, Land Department inspection photo 3, 16 July 2025
  • Mackerel Tower construction site, Land Department inspection photo 4, 16 July 2025

22 March 2025

6.5%+6.5 pts

  • Mackerel Tower construction site, Land Department inspection photo 1, 22 March 2025
  • Mackerel Tower construction site, Land Department inspection photo 2, 22 March 2025
  • Mackerel Tower construction site, Land Department inspection photo 3, 22 March 2025
  • Mackerel Tower construction site, Land Department inspection photo 4, 22 March 2025

31 October 2024

0%

  • Mackerel Tower construction site, Land Department inspection photo 1, 31 October 2024
  • Mackerel Tower construction site, Land Department inspection photo 2, 31 October 2024

All 37 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Tarrad Development has 4 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Mackerel Tower?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Mackerel Tower be completed?
The completion date registered with the Dubai Land Department is April 2026. At the pace of its recent inspections the site would reach 100% around February 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Mackerel Tower is built?
46%, measured at the Land Department site inspection on 20 July 2026. The Land Department engineers have inspected the site 6 times since October 2024.
Is Mackerel Tower delayed?
Yes. Its registered completion date of April 2026 has passed and the Land Department still lists it as under construction.
Who is building Mackerel Tower?
The registered developer is Tarrad Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Mackerel Tower?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.