Mackerel Tower construction progress

Mackerel Tower in Palm Deira was registered to complete in April 2026 and is still under construction. At the last site inspection, in October 2026, it was 57% built. The developer is Tarrad Development.

57%

Built, at the site inspection of 20 October 2026

8 months past its registered completion date

Registered completion date
April 2026
Finish at recent pace
December 2027
Construction started
November 2024
First registered
November 2024
Community
Palm Deira
Units
62
Escrow bank
First Abu Dhabi Bank
Name in Arabic
برج ماكريل
Project number
3351
Site inspections
7

Schedule

Mackerel Tower was registered to complete in April 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 3.1 points a month. Kept at that rate, the site would reach 100% around December 2027.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 October 2026

57%+11 pts

  • Mackerel Tower construction site, inspection photo 1, 20 October 2026
  • Mackerel Tower construction site, inspection photo 2, 20 October 2026
  • Mackerel Tower construction site, inspection photo 3, 20 October 2026
  • Mackerel Tower construction site, inspection photo 4, 20 October 2026

20 July 2026

46%+10 pts

  • Mackerel Tower construction site, inspection photo 1, 20 July 2026
  • Mackerel Tower construction site, inspection photo 2, 20 July 2026
  • Mackerel Tower construction site, inspection photo 3, 20 July 2026
  • Mackerel Tower construction site, inspection photo 4, 20 July 2026

1 April 2026

35%+9.9 pts

  • Mackerel Tower construction site, inspection photo 1, 1 April 2026
  • Mackerel Tower construction site, inspection photo 2, 1 April 2026
  • Mackerel Tower construction site, inspection photo 3, 1 April 2026
  • Mackerel Tower construction site, inspection photo 4, 1 April 2026

15 December 2025

25%+16 pts

  • Mackerel Tower construction site, inspection photo 1, 15 December 2025
  • Mackerel Tower construction site, inspection photo 2, 15 December 2025
  • Mackerel Tower construction site, inspection photo 3, 15 December 2025
  • Mackerel Tower construction site, inspection photo 4, 15 December 2025

16 July 2025

9.3%+2.9 pts

  • Mackerel Tower construction site, inspection photo 1, 16 July 2025
  • Mackerel Tower construction site, inspection photo 2, 16 July 2025
  • Mackerel Tower construction site, inspection photo 3, 16 July 2025
  • Mackerel Tower construction site, inspection photo 4, 16 July 2025

22 March 2025

6.5%+6.5 pts

  • Mackerel Tower construction site, inspection photo 1, 22 March 2025
  • Mackerel Tower construction site, inspection photo 2, 22 March 2025
  • Mackerel Tower construction site, inspection photo 3, 22 March 2025
  • Mackerel Tower construction site, inspection photo 4, 22 March 2025

31 October 2024

0%

  • Mackerel Tower construction site, inspection photo 1, 31 October 2024
  • Mackerel Tower construction site, inspection photo 2, 31 October 2024

All 49 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Tarrad Development has 4 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Mackerel Tower?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Mackerel Tower handover date?
The registered completion date was April 2026, and the register still lists Mackerel Tower as under construction. At the pace of its recent inspections the site would reach 100% around December 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Mackerel Tower?
Mackerel Tower was 57% built at the site inspection on 20 October 2026. The site has been inspected 7 times since October 2024. The Land Department took 49 site photos at its inspections.
Is Mackerel Tower delayed?
Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
Who is building Mackerel Tower?
The registered developer is Tarrad Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Mackerel Tower?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.