Mackerel Tower construction progress
Mackerel Tower in Palm Deira is 46% built at the Land Department inspection of July 2026. Developer Tarrad Development. Completion registered for April 2026.
46%
Built, at the Land Department site inspection of 20 July 2026
6 months past its registered completion date
- Completion date (Land Department)
- April 2026
- Finish at recent pace
- February 2028
- Construction started
- November 2024
- Registered with the Land Department
- November 2024
- Developer
- Tarrad Development
- Community
- Palm Deira
- Units
- 62
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- برج ماكريل
- Land Department project number
- 3351
- Land Department site inspections
- 6
Schedule
Mackerel Tower was registered to complete in April 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 2.9 points a month. Kept at that rate, the site would reach 100% around February 2028.
Site inspections
20 July 2026
46%+10 pts
1 April 2026
35%+9.9 pts
15 December 2025
25%+16 pts
16 July 2025
9.3%+2.9 pts
22 March 2025
6.5%+6.5 pts
31 October 2024
0%
Context
Palm Deira has 95 projects under construction, 22% built on average.
Tarrad Development has 4 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Mackerel Tower?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Mackerel Tower be completed?
- The completion date registered with the Dubai Land Department is April 2026. At the pace of its recent inspections the site would reach 100% around February 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Mackerel Tower is built?
- 46%, measured at the Land Department site inspection on 20 July 2026. The Land Department engineers have inspected the site 6 times since October 2024.
- Is Mackerel Tower delayed?
- Yes. Its registered completion date of April 2026 has passed and the Land Department still lists it as under construction.
- Who is building Mackerel Tower?
- The registered developer is Tarrad Development. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Mackerel Tower?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Celesto TowerAlso by Tarrad Development. 3.9%, Due December 2027.
- Celesto Tower 2Also by Tarrad Development. 0%, Due June 2028.
- Celesto Tower 3Also by Tarrad Development. 0%.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)