Park Field construction progress

The register lists Park Field in Dubai Hills Estate as complete, with a registered completion date of December 2025. Its last site inspection on record was in July 2025. The developer is Dubai Hills Estate.

100%

Built, at the site inspection of 29 July 2025

Construction complete

Registered completion date
December 2025
Construction started
October 2022
First registered
June 2022
Units
306
Escrow bank
Emirates Islamic Bank
Name in Arabic
بارك فيلد
Project number
2404
Site inspections
7

Schedule

The register lists Park Field as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202320242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

29 July 2025

100%+9.8 pts

  • Park Field construction site, inspection photo 1, 29 July 2025
  • Park Field construction site, inspection photo 2, 29 July 2025
  • Park Field construction site, inspection photo 3, 29 July 2025
  • Park Field construction site, inspection photo 4, 29 July 2025

14 April 2025

90%+28 pts

  • Park Field construction site, inspection photo 1, 14 April 2025
  • Park Field construction site, inspection photo 2, 14 April 2025
  • Park Field construction site, inspection photo 3, 14 April 2025
  • Park Field construction site, inspection photo 4, 14 April 2025

6 September 2024

62%+21 pts

  • Park Field construction site, inspection photo 1, 6 September 2024
  • Park Field construction site, inspection photo 2, 6 September 2024
  • Park Field construction site, inspection photo 3, 6 September 2024
  • Park Field construction site, inspection photo 4, 6 September 2024

25 April 2024

41%+27 pts

  • Park Field construction site, inspection photo 1, 25 April 2024
  • Park Field construction site, inspection photo 2, 25 April 2024
  • Park Field construction site, inspection photo 3, 25 April 2024
  • Park Field construction site, inspection photo 4, 25 April 2024

6 November 2023

14%+7.9 pts

  • Park Field construction site, inspection photo 1, 6 November 2023
  • Park Field construction site, inspection photo 2, 6 November 2023
  • Park Field construction site, inspection photo 3, 6 November 2023
  • Park Field construction site, inspection photo 4, 6 November 2023

4 July 2023

6.0%+3.5 pts

  • Park Field construction site, inspection photo 1, 4 July 2023
  • Park Field construction site, inspection photo 2, 4 July 2023
  • Park Field construction site, inspection photo 3, 4 July 2023
  • Park Field construction site, inspection photo 4, 4 July 2023

30 January 2023

2.5%

  • Park Field construction site, inspection photo 1, 30 January 2023
  • Park Field construction site, inspection photo 2, 30 January 2023
  • Park Field construction site, inspection photo 3, 30 January 2023
  • Park Field construction site, inspection photo 4, 30 January 2023

All 58 site photos, by inspection date

Context

Dubai Hills Estate has 19 projects under construction, 44% built on average.

Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Park Field?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Park Field handover date?
Construction of Park Field is recorded as complete, with a registered completion date of December 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Park Field?
Park Field was 100% built at the site inspection on 29 July 2025. The site has been inspected 7 times since January 2023. The Land Department took 58 site photos at its inspections.
Is Park Field delayed?
The register lists construction as complete.
Who is building Park Field?
The registered developer is Dubai Hills Estate. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for Park Field?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.