Keturah Resort construction progress

Keturah Resort in Dubai Health Care City Phase 2 is 15% built at the Land Department inspection of July 2026. Developer Mag Of Life. Completion registered for February 2026.

15%

Built, at the Land Department site inspection of 30 July 2026

8 months past its registered completion date

Completion date (Land Department)
February 2026
Finish at recent pace
August 2040
Construction started
January 2018
Registered with the Land Department
December 2017
Developer
Mag Of Life
Units
243
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
منتجع كتوراه
Land Department project number
1986
Land Department site inspections
13

Schedule

Keturah Resort was registered to complete in February 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 0.5 points a month. Kept at that rate, the site would reach 100% around August 2040.

0%25%50%75%100%2019202120232025
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 July 2026

15%+1.6 pts

  • Keturah Resort construction site, Land Department inspection photo 1, 30 July 2026
  • Keturah Resort construction site, Land Department inspection photo 2, 30 July 2026
  • Keturah Resort construction site, Land Department inspection photo 3, 30 July 2026
  • Keturah Resort construction site, Land Department inspection photo 4, 30 July 2026

24 April 2026

14%+3.7 pts

  • Keturah Resort construction site, Land Department inspection photo 1, 24 April 2026
  • Keturah Resort construction site, Land Department inspection photo 2, 24 April 2026
  • Keturah Resort construction site, Land Department inspection photo 3, 24 April 2026
  • Keturah Resort construction site, Land Department inspection photo 4, 24 April 2026

11 February 2025

10%+1.3 pts

  • Keturah Resort construction site, Land Department inspection photo 1, 11 February 2025
  • Keturah Resort construction site, Land Department inspection photo 2, 11 February 2025
  • Keturah Resort construction site, Land Department inspection photo 3, 11 February 2025
  • Keturah Resort construction site, Land Department inspection photo 4, 11 February 2025

6 June 2024

8.8%+1.1 pts

  • Keturah Resort construction site, Land Department inspection photo 1, 6 June 2024
  • Keturah Resort construction site, Land Department inspection photo 2, 6 June 2024
  • Keturah Resort construction site, Land Department inspection photo 3, 6 June 2024
  • Keturah Resort construction site, Land Department inspection photo 4, 6 June 2024

20 March 2024

7.7%+2.7 pts

  • Keturah Resort construction site, Land Department inspection photo 1, 20 March 2024
  • Keturah Resort construction site, Land Department inspection photo 2, 20 March 2024
  • Keturah Resort construction site, Land Department inspection photo 3, 20 March 2024
  • Keturah Resort construction site, Land Department inspection photo 4, 20 March 2024

2 October 2023

5.0%+0.2 pts

  • Keturah Resort construction site, Land Department inspection photo 1, 2 October 2023
  • Keturah Resort construction site, Land Department inspection photo 2, 2 October 2023
  • Keturah Resort construction site, Land Department inspection photo 3, 2 October 2023
  • Keturah Resort construction site, Land Department inspection photo 4, 2 October 2023

5 May 2023

4.8%+0.1 pts

  • Keturah Resort construction site, Land Department inspection photo 1, 5 May 2023
  • Keturah Resort construction site, Land Department inspection photo 2, 5 May 2023
  • Keturah Resort construction site, Land Department inspection photo 3, 5 May 2023
  • Keturah Resort construction site, Land Department inspection photo 4, 5 May 2023

16 September 2022

4.7%

  • Keturah Resort construction site, Land Department inspection photo 1, 16 September 2022
  • Keturah Resort construction site, Land Department inspection photo 2, 16 September 2022
  • Keturah Resort construction site, Land Department inspection photo 3, 16 September 2022
  • Keturah Resort construction site, Land Department inspection photo 4, 16 September 2022

11 May 2022

4.7%+1.0 pts

  • Keturah Resort construction site, Land Department inspection photo 1, 11 May 2022
  • Keturah Resort construction site, Land Department inspection photo 2, 11 May 2022
  • Keturah Resort construction site, Land Department inspection photo 3, 11 May 2022
  • Keturah Resort construction site, Land Department inspection photo 4, 11 May 2022

26 October 2021

3.7%

  • Keturah Resort construction site, Land Department inspection photo 1, 26 October 2021
  • Keturah Resort construction site, Land Department inspection photo 2, 26 October 2021
  • Keturah Resort construction site, Land Department inspection photo 3, 26 October 2021
  • Keturah Resort construction site, Land Department inspection photo 4, 26 October 2021

All 85 site photos, by inspection date

Context

Dubai Health Care City Phase 2 has 3 projects under construction, 51% built on average. Keturah Resort is behind that average.

Own a unit in Keturah Resort?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Keturah Resort be completed?
The completion date registered with the Dubai Land Department is February 2026. At the pace of its recent inspections the site would reach 100% around August 2040. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Keturah Resort is built?
15%, measured at the Land Department site inspection on 30 July 2026. The Land Department engineers have inspected the site 13 times since July 2018.
Is Keturah Resort delayed?
Yes. Its registered completion date of February 2026 has passed and the Land Department still lists it as under construction.
Who is building Keturah Resort?
The registered developer is Mag Of Life.
Which bank holds the escrow account for Keturah Resort?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.