Keturah Resort construction progress
Keturah Resort in Dubai Health Care City Phase 2 was registered to complete in February 2026 and is still under construction. At the last site inspection, in November 2026, it was 16% built. The developer is Mag Of Life.
16%
Built, at the site inspection of 5 November 2026
9 months past its registered completion date
- Registered completion date
- February 2026
- Finish at recent pace
- October 2048
- Construction started
- January 2018
- First registered
- December 2017
- Developer
- Mag Of Life
- Community
- Dubai Health Care City Phase 2
- Units
- 243
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- منتجع كتوراه
- Project number
- 1986
- Site inspections
- 14
Schedule
Keturah Resort was registered to complete in February 2026, 9 months ago, and is still under construction. Over the last year of inspections it has added about 0.3 points a month. Kept at that rate, the site would reach 100% around October 2048.
Site inspections
5 November 2026
16%+0.4 pts
30 July 2026
15%+1.6 pts
24 April 2026
14%+3.7 pts
11 February 2025
10%+1.3 pts
6 June 2024
8.8%+1.1 pts
20 March 2024
7.7%+2.7 pts
2 October 2023
5.0%+0.2 pts
5 May 2023
4.8%+0.1 pts
16 September 2022
4.7%
11 May 2022
4.7%+1.0 pts
Context
Dubai Health Care City Phase 2 has 3 projects under construction, 51% built on average.
Own a unit in Keturah Resort?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Keturah Resort handover date?
- The registered completion date was February 2026, and the register still lists Keturah Resort as under construction. At the pace of its recent inspections the site would reach 100% around October 2048. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Keturah Resort?
- Keturah Resort was 16% built at the site inspection on 5 November 2026. The site has been inspected 14 times since July 2018. The Land Department took 95 site photos at its inspections.
- Is Keturah Resort delayed?
- Yes. Its registered completion date of February 2026 has passed and the project is still listed as under construction.
- Who is building Keturah Resort?
- The registered developer is Mag Of Life.
- Which bank holds the escrow account for Keturah Resort?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Adeba AziziNearby in Dubai Health Care City Phase 2. 75%.
- Binghatti StarlightNearby in Dubai Health Care City Phase 2. 63%, Due March 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

















.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)