Keturah Resort construction progress
Keturah Resort in Dubai Health Care City Phase 2 is 15% built at the Land Department inspection of July 2026. Developer Mag Of Life. Completion registered for February 2026.
15%
Built, at the Land Department site inspection of 30 July 2026
8 months past its registered completion date
- Completion date (Land Department)
- February 2026
- Finish at recent pace
- August 2040
- Construction started
- January 2018
- Registered with the Land Department
- December 2017
- Developer
- Mag Of Life
- Community
- Dubai Health Care City Phase 2
- Units
- 243
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- منتجع كتوراه
- Land Department project number
- 1986
- Land Department site inspections
- 13
Schedule
Keturah Resort was registered to complete in February 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 0.5 points a month. Kept at that rate, the site would reach 100% around August 2040.
Site inspections
30 July 2026
15%+1.6 pts
24 April 2026
14%+3.7 pts
11 February 2025
10%+1.3 pts
6 June 2024
8.8%+1.1 pts
20 March 2024
7.7%+2.7 pts
2 October 2023
5.0%+0.2 pts
5 May 2023
4.8%+0.1 pts
16 September 2022
4.7%
11 May 2022
4.7%+1.0 pts
26 October 2021
3.7%
Context
Dubai Health Care City Phase 2 has 3 projects under construction, 51% built on average. Keturah Resort is behind that average.
Own a unit in Keturah Resort?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Keturah Resort be completed?
- The completion date registered with the Dubai Land Department is February 2026. At the pace of its recent inspections the site would reach 100% around August 2040. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Keturah Resort is built?
- 15%, measured at the Land Department site inspection on 30 July 2026. The Land Department engineers have inspected the site 13 times since July 2018.
- Is Keturah Resort delayed?
- Yes. Its registered completion date of February 2026 has passed and the Land Department still lists it as under construction.
- Who is building Keturah Resort?
- The registered developer is Mag Of Life.
- Which bank holds the escrow account for Keturah Resort?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


















.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)


.jpg&w=3840&q=75)
.jpg&w=3840&q=75)