Binghatti Gateway construction progress

The register lists Binghatti Gateway in Dubai Health Care City Phase 2 as complete, with a registered completion date of June 2021. Its last site inspection on record was in July 2021. The developer is Binghatti Developers.

100%

Built, at the site inspection of 11 July 2021

Construction complete

Registered completion date
June 2021
Construction started
January 2019
First registered
December 2018
Units
182
Escrow bank
Sharjah Islamic Bank
Name in Arabic
بن غاطي جيت وي
Project number
2117
Site inspections
4

Schedule

The register lists Binghatti Gateway as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

11 July 2021

100%+55 pts

  • Binghatti Gateway construction site, inspection photo 1, 11 July 2021
  • Binghatti Gateway construction site, inspection photo 2, 11 July 2021
  • Binghatti Gateway construction site, inspection photo 3, 11 July 2021
  • Binghatti Gateway construction site, inspection photo 4, 11 July 2021

17 November 2020

45%+28 pts

  • Binghatti Gateway construction site, inspection photo 1, 17 November 2020
  • Binghatti Gateway construction site, inspection photo 2, 17 November 2020
  • Binghatti Gateway construction site, inspection photo 3, 17 November 2020
  • Binghatti Gateway construction site, inspection photo 4, 17 November 2020

22 March 2020

17%+15 pts

  • Binghatti Gateway construction site, inspection photo 1, 22 March 2020
  • Binghatti Gateway construction site, inspection photo 2, 22 March 2020
  • Binghatti Gateway construction site, inspection photo 3, 22 March 2020
  • Binghatti Gateway construction site, inspection photo 4, 22 March 2020

23 October 2019

2.7%

  • Binghatti Gateway construction site, inspection photo 1, 23 October 2019
  • Binghatti Gateway construction site, inspection photo 2, 23 October 2019
  • Binghatti Gateway construction site, inspection photo 3, 23 October 2019
  • Binghatti Gateway construction site, inspection photo 4, 23 October 2019

All 36 site photos, by inspection date

Context

Dubai Health Care City Phase 2 has 3 projects under construction, 51% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Gateway?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Binghatti Gateway handover date?
Construction of Binghatti Gateway is recorded as complete, with a registered completion date of June 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Binghatti Gateway?
Binghatti Gateway was 100% built at the site inspection on 11 July 2021. The site has been inspected 4 times since October 2019. The Land Department took 36 site photos at its inspections.
Is Binghatti Gateway delayed?
The register lists construction as complete.
Who is building Binghatti Gateway?
The registered developer is Binghatti Developers. It has 38 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Gateway?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.