Valo construction progress

No completion date is registered for Valo in Dubai Creek Harbour yet. At the last site inspection, in November 2026, it was 91% built. The developer is Dubai Creek Harbour.

91%

Built, at the site inspection of 16 November 2026

Finish at recent pace
January 2027
Construction started
August 2024
First registered
April 2024
Units
291
Escrow bank
Emirates Islamic Bank
Name in Arabic
فالو
Project number
3033
Site inspections
9

Schedule

Since December 2025 Valo has added about 5.1 points a month. At that rate the site reaches 100% around January 2027. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

16 November 2026

91%+25 pts

  • Valo construction site, inspection photo 1, 16 November 2026
  • Valo construction site, inspection photo 2, 16 November 2026
  • Valo construction site, inspection photo 3, 16 November 2026
  • Valo construction site, inspection photo 4, 16 November 2026

25 June 2026

66%+15 pts

  • Valo construction site, inspection photo 1, 25 June 2026
  • Valo construction site, inspection photo 2, 25 June 2026
  • Valo construction site, inspection photo 3, 25 June 2026
  • Valo construction site, inspection photo 4, 25 June 2026

17 March 2026

51%+18 pts

  • Valo construction site, inspection photo 1, 17 March 2026
  • Valo construction site, inspection photo 2, 17 March 2026
  • Valo construction site, inspection photo 3, 17 March 2026
  • Valo construction site, inspection photo 4, 17 March 2026

4 December 2025

33%+6.5 pts

  • Valo construction site, inspection photo 1, 4 December 2025
  • Valo construction site, inspection photo 2, 4 December 2025
  • Valo construction site, inspection photo 3, 4 December 2025
  • Valo construction site, inspection photo 4, 4 December 2025

17 October 2025

27%+12 pts

  • Valo construction site, inspection photo 1, 17 October 2025
  • Valo construction site, inspection photo 2, 17 October 2025
  • Valo construction site, inspection photo 3, 17 October 2025
  • Valo construction site, inspection photo 4, 17 October 2025

11 June 2025

15%+4.7 pts

  • Valo construction site, inspection photo 1, 11 June 2025
  • Valo construction site, inspection photo 2, 11 June 2025
  • Valo construction site, inspection photo 3, 11 June 2025
  • Valo construction site, inspection photo 4, 11 June 2025

11 March 2025

10%+5.3 pts

  • Valo construction site, inspection photo 1, 11 March 2025
  • Valo construction site, inspection photo 2, 11 March 2025
  • Valo construction site, inspection photo 3, 11 March 2025
  • Valo construction site, inspection photo 4, 11 March 2025

4 October 2024

5.1%+5.1 pts

  • Valo construction site, inspection photo 1, 4 October 2024
  • Valo construction site, inspection photo 2, 4 October 2024
  • Valo construction site, inspection photo 3, 4 October 2024

1 April 2024

0%

  • Valo construction site, inspection photo 1, 1 April 2024
  • Valo construction site, inspection photo 2, 1 April 2024
  • Valo construction site, inspection photo 3, 1 April 2024

All 59 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 53% built on average.

Dubai Creek Harbour has 15 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Valo?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Valo handover date?
No completion date is on record for Valo yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Valo?
Valo was 91% built at the site inspection on 16 November 2026. The site has been inspected 9 times since April 2024. The Land Department took 59 site photos at its inspections.
Who is building Valo?
The registered developer is Dubai Creek Harbour. It has 14 other projects under construction in Dubai.
Which bank holds the escrow account for Valo?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.