Valo construction photos
59 photos from 9 site inspections, newest first. The percentage is how much of Valo was built on the day of each visit.
16 November 202691% built
25 June 202666% built
17 March 202651% built
4 December 202533% built
17 October 202527% built
11 June 202515% built
11 March 202510% built
4 October 20245.1% built
1 April 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.