Creek Waters 2 construction progress
Creek Waters 2 in Dubai Creek Harbour is 82% built at the Land Department inspection of July 2026. Developer The Lagoons Phase One. Completion registered for December 2027.
82%
Built, at the Land Department site inspection of 31 July 2026
On pace for its date
- Completion date (Land Department)
- December 2027
- Finish at recent pace
- March 2027
- Construction started
- August 2023
- Registered with the Land Department
- May 2023
- Developer
- The Lagoons Phase One
- Community
- Dubai Creek Harbour
- Units
- 455
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- كريك واترز 2
- Land Department project number
- 2634
- Land Department site inspections
- 10
Schedule
Since December 2025 Creek Waters 2 has added about 2.5 points a month. That puts 100% around March 2027, within three months of its registered completion date of December 2027.
Site inspections
31 July 2026
82%+8.0 pts
20 April 2026
74%+11 pts
9 December 2025
63%+16 pts
23 July 2025
47%+13 pts
24 April 2025
34%+11 pts
23 January 2025
23%+8.8 pts
15 October 2024
14%+10 pts
8 May 2024
3.4%+3.2 pts
25 October 2023
0.2%+0.2 pts
6 April 2023
0%
Context
Dubai Creek Harbour has 14 projects under construction, 41% built on average.
The Lagoons Phase One has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Creek Waters 2?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Creek Waters 2 be completed?
- The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around March 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Creek Waters 2 is built?
- 82%, measured at the Land Department site inspection on 31 July 2026. The Land Department engineers have inspected the site 10 times since April 2023.
- Is Creek Waters 2 delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2027.
- Who is building Creek Waters 2?
- The registered developer is The Lagoons Phase One. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Creek Waters 2?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Creek WatersAlso by The Lagoons Phase One. 81%, Due September 2027.
- AeonNearby in Dubai Creek Harbour. 90%.
- OriaNearby in Dubai Creek Harbour. 71%.
- ValoNearby in Dubai Creek Harbour. 66%.
- ArloNearby in Dubai Creek Harbour. 35%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.















.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)