Creek Waters construction progress

Creek Waters in Dubai Creek Harbour is 81% built at the Land Department inspection of August 2026. Developer The Lagoons Phase One. Completion registered for September 2027.

81%

Built, at the Land Department site inspection of 3 August 2026

On pace for its date

Completion date (Land Department)
September 2027
Finish at recent pace
March 2027
Construction started
August 2023
Registered with the Land Department
March 2023
Developer
The Lagoons Phase One
Units
453
Escrow bank
First Abu Dhabi Bank
Name in Arabic
كريك واترز
Land Department project number
2614
Land Department site inspections
10

Schedule

Since December 2025 Creek Waters has added about 2.4 points a month. That puts 100% around March 2027, within three months of its registered completion date of September 2027.

0%25%50%75%100%2024202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

3 August 2026

81%+8.9 pts

  • Creek Waters construction site, Land Department inspection photo 1, 3 August 2026
  • Creek Waters construction site, Land Department inspection photo 2, 3 August 2026
  • Creek Waters construction site, Land Department inspection photo 3, 3 August 2026
  • Creek Waters construction site, Land Department inspection photo 4, 3 August 2026

10 April 2026

72%+9.9 pts

  • Creek Waters construction site, Land Department inspection photo 1, 10 April 2026
  • Creek Waters construction site, Land Department inspection photo 2, 10 April 2026
  • Creek Waters construction site, Land Department inspection photo 3, 10 April 2026
  • Creek Waters construction site, Land Department inspection photo 4, 10 April 2026

9 December 2025

62%+12 pts

  • Creek Waters construction site, Land Department inspection photo 1, 9 December 2025
  • Creek Waters construction site, Land Department inspection photo 2, 9 December 2025
  • Creek Waters construction site, Land Department inspection photo 3, 9 December 2025
  • Creek Waters construction site, Land Department inspection photo 4, 9 December 2025

22 July 2025

50%+15 pts

  • Creek Waters construction site, Land Department inspection photo 1, 22 July 2025
  • Creek Waters construction site, Land Department inspection photo 2, 22 July 2025
  • Creek Waters construction site, Land Department inspection photo 3, 22 July 2025
  • Creek Waters construction site, Land Department inspection photo 4, 22 July 2025

24 April 2025

34%+9.7 pts

  • Creek Waters construction site, Land Department inspection photo 1, 24 April 2025
  • Creek Waters construction site, Land Department inspection photo 2, 24 April 2025
  • Creek Waters construction site, Land Department inspection photo 3, 24 April 2025
  • Creek Waters construction site, Land Department inspection photo 4, 24 April 2025

23 January 2025

25%+14 pts

  • Creek Waters construction site, Land Department inspection photo 1, 23 January 2025
  • Creek Waters construction site, Land Department inspection photo 2, 23 January 2025
  • Creek Waters construction site, Land Department inspection photo 3, 23 January 2025
  • Creek Waters construction site, Land Department inspection photo 4, 23 January 2025

11 September 2024

11%+7.7 pts

  • Creek Waters construction site, Land Department inspection photo 1, 11 September 2024
  • Creek Waters construction site, Land Department inspection photo 2, 11 September 2024
  • Creek Waters construction site, Land Department inspection photo 3, 11 September 2024
  • Creek Waters construction site, Land Department inspection photo 4, 11 September 2024

8 May 2024

3.6%+3.4 pts

  • Creek Waters construction site, Land Department inspection photo 1, 8 May 2024
  • Creek Waters construction site, Land Department inspection photo 2, 8 May 2024
  • Creek Waters construction site, Land Department inspection photo 3, 8 May 2024

25 October 2023

0.2%+0.2 pts

  • Creek Waters construction site, Land Department inspection photo 1, 25 October 2023
  • Creek Waters construction site, Land Department inspection photo 2, 25 October 2023
  • Creek Waters construction site, Land Department inspection photo 3, 25 October 2023
  • Creek Waters construction site, Land Department inspection photo 4, 25 October 2023

29 March 2023

0%

  • Creek Waters construction site, Land Department inspection photo 1, 29 March 2023
  • Creek Waters construction site, Land Department inspection photo 2, 29 March 2023
  • Creek Waters construction site, Land Department inspection photo 3, 29 March 2023

All 60 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 41% built on average. Creek Waters is ahead of that average.

The Lagoons Phase One has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Creek Waters?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Creek Waters be completed?
The completion date registered with the Dubai Land Department is September 2027. At the pace of its recent inspections the site would reach 100% around March 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Creek Waters is built?
81%, measured at the Land Department site inspection on 3 August 2026. The Land Department engineers have inspected the site 10 times since March 2023.
Is Creek Waters delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of September 2027.
Who is building Creek Waters?
The registered developer is The Lagoons Phase One. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Creek Waters?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.