Creek Waters construction progress
Creek Waters in Dubai Creek Harbour is 81% built at the Land Department inspection of August 2026. Developer The Lagoons Phase One. Completion registered for September 2027.
81%
Built, at the Land Department site inspection of 3 August 2026
On pace for its date
- Completion date (Land Department)
- September 2027
- Finish at recent pace
- March 2027
- Construction started
- August 2023
- Registered with the Land Department
- March 2023
- Developer
- The Lagoons Phase One
- Community
- Dubai Creek Harbour
- Units
- 453
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- كريك واترز
- Land Department project number
- 2614
- Land Department site inspections
- 10
Schedule
Since December 2025 Creek Waters has added about 2.4 points a month. That puts 100% around March 2027, within three months of its registered completion date of September 2027.
Site inspections
3 August 2026
81%+8.9 pts
10 April 2026
72%+9.9 pts
9 December 2025
62%+12 pts
22 July 2025
50%+15 pts
24 April 2025
34%+9.7 pts
23 January 2025
25%+14 pts
11 September 2024
11%+7.7 pts
8 May 2024
3.6%+3.4 pts
25 October 2023
0.2%+0.2 pts
29 March 2023
0%
Context
Dubai Creek Harbour has 14 projects under construction, 41% built on average. Creek Waters is ahead of that average.
The Lagoons Phase One has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Creek Waters?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Creek Waters be completed?
- The completion date registered with the Dubai Land Department is September 2027. At the pace of its recent inspections the site would reach 100% around March 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Creek Waters is built?
- 81%, measured at the Land Department site inspection on 3 August 2026. The Land Department engineers have inspected the site 10 times since March 2023.
- Is Creek Waters delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of September 2027.
- Who is building Creek Waters?
- The registered developer is The Lagoons Phase One. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Creek Waters?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Creek Waters 2Also by The Lagoons Phase One. 82%, Due December 2027.
- AeonNearby in Dubai Creek Harbour. 90%.
- OriaNearby in Dubai Creek Harbour. 71%.
- ValoNearby in Dubai Creek Harbour. 66%.
- ArloNearby in Dubai Creek Harbour. 35%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.



















.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)