Arlo construction progress

No completion date is registered for Arlo in Dubai Creek Harbour yet. At the last site inspection, in November 2026, it was 72% built. The developer is Dubai Creek Harbour.

72%

Built, at the site inspection of 10 November 2026

Finish at recent pace
April 2027
Construction started
October 2024
First registered
May 2024
Units
434
Escrow bank
Emirates Islamic Bank
Name in Arabic
أرلو
Project number
3104
Site inspections
7

Schedule

Since February 2026 Arlo has added about 5.0 points a month. At that rate the site reaches 100% around April 2027. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

10 November 2026

72%+36 pts

  • Arlo construction site, inspection photo 1, 10 November 2026
  • Arlo construction site, inspection photo 2, 10 November 2026
  • Arlo construction site, inspection photo 3, 10 November 2026
  • Arlo construction site, inspection photo 4, 10 November 2026

3 June 2026

35%+9.4 pts

  • Arlo construction site, inspection photo 1, 3 June 2026
  • Arlo construction site, inspection photo 2, 3 June 2026
  • Arlo construction site, inspection photo 3, 3 June 2026
  • Arlo construction site, inspection photo 4, 3 June 2026

4 February 2026

26%+11 pts

  • Arlo construction site, inspection photo 1, 4 February 2026
  • Arlo construction site, inspection photo 2, 4 February 2026
  • Arlo construction site, inspection photo 3, 4 February 2026
  • Arlo construction site, inspection photo 4, 4 February 2026

7 October 2025

15%+6.1 pts

  • Arlo construction site, inspection photo 1, 7 October 2025
  • Arlo construction site, inspection photo 2, 7 October 2025
  • Arlo construction site, inspection photo 3, 7 October 2025

22 May 2025

8.7%+2.3 pts

  • Arlo construction site, inspection photo 1, 22 May 2025
  • Arlo construction site, inspection photo 2, 22 May 2025
  • Arlo construction site, inspection photo 3, 22 May 2025
  • Arlo construction site, inspection photo 4, 22 May 2025

29 November 2024

6.5%+6.5 pts

  • Arlo construction site, inspection photo 1, 29 November 2024
  • Arlo construction site, inspection photo 2, 29 November 2024
  • Arlo construction site, inspection photo 3, 29 November 2024

23 May 2024

0%

  • Arlo construction site, inspection photo 1, 23 May 2024
  • Arlo construction site, inspection photo 2, 23 May 2024

All 38 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 53% built on average.

Dubai Creek Harbour has 15 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Arlo?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Arlo handover date?
No completion date is on record for Arlo yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Arlo?
Arlo was 72% built at the site inspection on 10 November 2026. The site has been inspected 7 times since May 2024. The Land Department took 38 site photos at its inspections.
Who is building Arlo?
The registered developer is Dubai Creek Harbour. It has 14 other projects under construction in Dubai.
Which bank holds the escrow account for Arlo?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.