Skip to content

Palace Residences Creek Blue construction progress

The registered completion date for Palace Residences Creek Blue in Dubai Creek Harbour is March 2029. At the last site inspection, in November 2026, it was 40% built. The developer is Dubai Creek Harbour.

40%

Built, at the site inspection of 5 November 2026

On pace for its date

Registered completion date
March 2029
Finish at recent pace
September 2028
Construction started
August 2024
First registered
June 2024
Units
512
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
بالاس رزيدنسز كريك بلو
Project number
3147
Site inspections
6

Schedule

Since November 2025 Palace Residences Creek Blue has added about 2.7 points a month. That puts 100% around September 2028, within three months of its registered completion date of March 2029.

0%25%50%75%100%20252026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 November 2026

40%+20 pts

  • Palace Residences Creek Blue construction site, inspection photo 1, 5 November 2026
  • Palace Residences Creek Blue construction site, inspection photo 2, 5 November 2026
  • Palace Residences Creek Blue construction site, inspection photo 3, 5 November 2026
  • Palace Residences Creek Blue construction site, inspection photo 4, 5 November 2026

9 June 2026

21%+3.8 pts

  • Palace Residences Creek Blue construction site, inspection photo 1, 9 June 2026
  • Palace Residences Creek Blue construction site, inspection photo 2, 9 June 2026
  • Palace Residences Creek Blue construction site, inspection photo 3, 9 June 2026
  • Palace Residences Creek Blue construction site, inspection photo 4, 9 June 2026

24 February 2026

17%+8.3 pts

  • Palace Residences Creek Blue construction site, inspection photo 1, 24 February 2026
  • Palace Residences Creek Blue construction site, inspection photo 2, 24 February 2026
  • Palace Residences Creek Blue construction site, inspection photo 3, 24 February 2026
  • Palace Residences Creek Blue construction site, inspection photo 4, 24 February 2026

11 November 2025

8.5%+6.9 pts

  • Palace Residences Creek Blue construction site, inspection photo 1, 11 November 2025
  • Palace Residences Creek Blue construction site, inspection photo 2, 11 November 2025
  • Palace Residences Creek Blue construction site, inspection photo 3, 11 November 2025
  • Palace Residences Creek Blue construction site, inspection photo 4, 11 November 2025

12 May 2025

1.6%+1.6 pts

  • Palace Residences Creek Blue construction site, inspection photo 1, 12 May 2025
  • Palace Residences Creek Blue construction site, inspection photo 2, 12 May 2025
  • Palace Residences Creek Blue construction site, inspection photo 3, 12 May 2025
  • Palace Residences Creek Blue construction site, inspection photo 4, 12 May 2025

19 June 2024

0%

  • Palace Residences Creek Blue construction site, inspection photo 1, 19 June 2024
  • Palace Residences Creek Blue construction site, inspection photo 2, 19 June 2024

All 29 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 53% built on average.

Dubai Creek Harbour has 15 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Palace Residences Creek Blue?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Palace Residences Creek Blue handover date?
The registered completion date is March 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Palace Residences Creek Blue?
Palace Residences Creek Blue was 40% built at the site inspection on 5 November 2026. The site has been inspected 6 times since June 2024. The Land Department took 29 site photos at its inspections.
Is Palace Residences Creek Blue delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2029.
Who is building Palace Residences Creek Blue?
The registered developer is Dubai Creek Harbour. It has 14 other projects under construction in Dubai.
Which bank holds the escrow account for Palace Residences Creek Blue?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.