Palace Residences - North construction progress

The register lists Palace Residences - North in Dubai Creek Harbour as complete, with a registered completion date of June 2027. Its last site inspection on record was in September 2025. The developer is The Lagoons Phase One.

100%

Built, at the site inspection of 8 September 2025

Construction complete

Registered completion date
June 2027
Construction started
July 2023
First registered
February 2023
Units
340
Escrow bank
First Abu Dhabi Bank
Name in Arabic
بالاس ريزيدنسز - نورث
Project number
2562
Site inspections
9

Schedule

The register lists Palace Residences - North as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2024202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 September 2025

100%+5.3 pts

  • Palace Residences - North construction site, inspection photo 1, 8 September 2025
  • Palace Residences - North construction site, inspection photo 2, 8 September 2025
  • Palace Residences - North construction site, inspection photo 3, 8 September 2025
  • Palace Residences - North construction site, inspection photo 4, 8 September 2025

18 July 2025

95%+22 pts

  • Palace Residences - North construction site, inspection photo 1, 18 July 2025
  • Palace Residences - North construction site, inspection photo 2, 18 July 2025
  • Palace Residences - North construction site, inspection photo 3, 18 July 2025
  • Palace Residences - North construction site, inspection photo 4, 18 July 2025

24 April 2025

72%+19 pts

  • Palace Residences - North construction site, inspection photo 1, 24 April 2025
  • Palace Residences - North construction site, inspection photo 2, 24 April 2025
  • Palace Residences - North construction site, inspection photo 3, 24 April 2025
  • Palace Residences - North construction site, inspection photo 4, 24 April 2025

9 January 2025

54%+24 pts

  • Palace Residences - North construction site, inspection photo 1, 9 January 2025
  • Palace Residences - North construction site, inspection photo 2, 9 January 2025
  • Palace Residences - North construction site, inspection photo 3, 9 January 2025
  • Palace Residences - North construction site, inspection photo 4, 9 January 2025

11 September 2024

30%+18 pts

  • Palace Residences - North construction site, inspection photo 1, 11 September 2024
  • Palace Residences - North construction site, inspection photo 2, 11 September 2024
  • Palace Residences - North construction site, inspection photo 3, 11 September 2024
  • Palace Residences - North construction site, inspection photo 4, 11 September 2024

7 May 2024

12%+6.5 pts

  • Palace Residences - North construction site, inspection photo 1, 7 May 2024
  • Palace Residences - North construction site, inspection photo 2, 7 May 2024
  • Palace Residences - North construction site, inspection photo 3, 7 May 2024
  • Palace Residences - North construction site, inspection photo 4, 7 May 2024

25 October 2023

5.2%+5.0 pts

  • Palace Residences - North construction site, inspection photo 1, 25 October 2023
  • Palace Residences - North construction site, inspection photo 2, 25 October 2023
  • Palace Residences - North construction site, inspection photo 3, 25 October 2023
  • Palace Residences - North construction site, inspection photo 4, 25 October 2023

10 July 2023

0.3%+0.3 pts

  • Palace Residences - North construction site, inspection photo 1, 10 July 2023
  • Palace Residences - North construction site, inspection photo 2, 10 July 2023
  • Palace Residences - North construction site, inspection photo 3, 10 July 2023
  • Palace Residences - North construction site, inspection photo 4, 10 July 2023

23 January 2023

0%

  • Palace Residences - North construction site, inspection photo 1, 23 January 2023
  • Palace Residences - North construction site, inspection photo 2, 23 January 2023
  • Palace Residences - North construction site, inspection photo 3, 23 January 2023

All 58 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 53% built on average.

The Lagoons Phase One has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Palace Residences - North?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Palace Residences - North handover date?
Construction of Palace Residences - North is recorded as complete, with a registered completion date of June 2027. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Palace Residences - North?
Palace Residences - North was 100% built at the site inspection on 8 September 2025. The site has been inspected 9 times since January 2023. The Land Department took 58 site photos at its inspections.
Is Palace Residences - North delayed?
The register lists construction as complete.
Who is building Palace Residences - North?
The registered developer is The Lagoons Phase One. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Palace Residences - North?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.