Palace Residences - North construction photos
58 photos from 9 site inspections, newest first. The percentage is how much of Palace Residences - North was built on the day of each visit.
8 September 2025100% built
18 July 202595% built
24 April 202572% built
9 January 202554% built
11 September 202430% built
7 May 202412% built
25 October 20235.2% built
10 July 20230.3% built
23 January 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.