Creekside 18 construction progress

The register lists Creekside 18 in Dubai Creek Harbour as complete, with a registered completion date of May 2020. Its last site inspection on record was in March 2021. The developer is The Lagoons Phase One.

100%

Built, at the site inspection of 14 March 2021

Construction complete

Registered completion date
May 2020
Construction started
March 2016
First registered
June 2015
Units
506
Escrow bank
Commercial Bank of Dubai
Name in Arabic
كريك سايد 18
Project number
1663
Site inspections
15

Schedule

The register lists Creekside 18 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20172018201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 March 2021

100%+1.4 pts

  • Creekside 18 construction site, inspection photo 1, 14 March 2021
  • Creekside 18 construction site, inspection photo 2, 14 March 2021
  • Creekside 18 construction site, inspection photo 3, 14 March 2021
  • Creekside 18 construction site, inspection photo 4, 14 March 2021

7 February 2021

99%+2.6 pts

  • Creekside 18 construction site, inspection photo 1, 7 February 2021
  • Creekside 18 construction site, inspection photo 2, 7 February 2021
  • Creekside 18 construction site, inspection photo 3, 7 February 2021
  • Creekside 18 construction site, inspection photo 4, 7 February 2021

27 July 2020

96%+2.3 pts

  • Creekside 18 construction site, inspection photo 1, 27 July 2020
  • Creekside 18 construction site, inspection photo 2, 27 July 2020
  • Creekside 18 construction site, inspection photo 3, 27 July 2020
  • Creekside 18 construction site, inspection photo 4, 27 July 2020

20 April 2020

94%+3.6 pts

  • Creekside 18 construction site, inspection photo 1, 20 April 2020
  • Creekside 18 construction site, inspection photo 2, 20 April 2020
  • Creekside 18 construction site, inspection photo 3, 20 April 2020
  • Creekside 18 construction site, inspection photo 4, 20 April 2020

5 January 2020

90%+10 pts

  • Creekside 18 construction site, inspection photo 1, 5 January 2020
  • Creekside 18 construction site, inspection photo 2, 5 January 2020
  • Creekside 18 construction site, inspection photo 3, 5 January 2020
  • Creekside 18 construction site, inspection photo 4, 5 January 2020

12 September 2019

80%+3.7 pts

  • Creekside 18 construction site, inspection photo 1, 12 September 2019
  • Creekside 18 construction site, inspection photo 2, 12 September 2019
  • Creekside 18 construction site, inspection photo 3, 12 September 2019
  • Creekside 18 construction site, inspection photo 4, 12 September 2019

25 July 2019

76%+8.8 pts

  • Creekside 18 construction site, inspection photo 1, 25 July 2019
  • Creekside 18 construction site, inspection photo 2, 25 July 2019
  • Creekside 18 construction site, inspection photo 3, 25 July 2019
  • Creekside 18 construction site, inspection photo 4, 25 July 2019

7 April 2019

68%+12 pts

  • Creekside 18 construction site, inspection photo 1, 7 April 2019
  • Creekside 18 construction site, inspection photo 2, 7 April 2019
  • Creekside 18 construction site, inspection photo 3, 7 April 2019
  • Creekside 18 construction site, inspection photo 4, 7 April 2019

2 January 2019

55%+5.4 pts

  • Creekside 18 construction site, inspection photo 1, 2 January 2019
  • Creekside 18 construction site, inspection photo 2, 2 January 2019
  • Creekside 18 construction site, inspection photo 3, 2 January 2019
  • Creekside 18 construction site, inspection photo 4, 2 January 2019

14 October 2018

50%+6.0 pts

  • Creekside 18 construction site, inspection photo 1, 14 October 2018
  • Creekside 18 construction site, inspection photo 2, 14 October 2018
  • Creekside 18 construction site, inspection photo 3, 14 October 2018
  • Creekside 18 construction site, inspection photo 4, 14 October 2018

All 149 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 53% built on average.

The Lagoons Phase One has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Creekside 18?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Creekside 18 handover date?
Construction of Creekside 18 is recorded as complete, with a registered completion date of May 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Creekside 18?
Creekside 18 was 100% built at the site inspection on 14 March 2021. The site has been inspected 15 times since December 2016. The Land Department took 149 site photos at its inspections.
Is Creekside 18 delayed?
The register lists construction as complete.
Who is building Creekside 18?
The registered developer is The Lagoons Phase One. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Creekside 18?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.