Creekside 18 construction photos

149 photos from 15 site inspections, newest first. The percentage is how much of Creekside 18 was built on the day of each visit.

14 March 2021100% built

7 February 202199% built

27 July 202096% built

20 April 202094% built

5 January 202090% built

12 September 201980% built

25 July 201976% built

7 April 201968% built

2 January 201955% built

14 October 201850% built

5 September 201844% built

10 May 201833% built

15 January 201822% built

30 July 201711% built

14 December 20164.7% built

Back to Creekside 18 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.