Skip to content

Creek Rise construction progress

The register lists Creek Rise in Dubai Creek Harbour as complete, with a registered completion date of June 2022. Its last site inspection on record was in December 2021. The developer is The Lagoons Phase One.

100%

Built, at the site inspection of 29 December 2021

Construction complete

Registered completion date
June 2022
Construction started
April 2017
First registered
January 2017
Units
547
Escrow bank
Emirates NBD
Name in Arabic
كريك ريس
Project number
1850
Site inspections
15

Schedule

The register lists Creek Rise as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20182019202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

29 December 2021

100%+4.5 pts

  • Creek Rise construction site, inspection photo 1, 29 December 2021
  • Creek Rise construction site, inspection photo 2, 29 December 2021
  • Creek Rise construction site, inspection photo 3, 29 December 2021
  • Creek Rise construction site, inspection photo 4, 29 December 2021

4 October 2021

96%+2.4 pts

  • Creek Rise construction site, inspection photo 1, 4 October 2021
  • Creek Rise construction site, inspection photo 2, 4 October 2021
  • Creek Rise construction site, inspection photo 3, 4 October 2021
  • Creek Rise construction site, inspection photo 4, 4 October 2021

29 June 2021

93%+6.3 pts

  • Creek Rise construction site, inspection photo 1, 29 June 2021
  • Creek Rise construction site, inspection photo 2, 29 June 2021
  • Creek Rise construction site, inspection photo 3, 29 June 2021
  • Creek Rise construction site, inspection photo 4, 29 June 2021

11 March 2021

87%+6.7 pts

  • Creek Rise construction site, inspection photo 1, 11 March 2021
  • Creek Rise construction site, inspection photo 2, 11 March 2021
  • Creek Rise construction site, inspection photo 3, 11 March 2021
  • Creek Rise construction site, inspection photo 4, 11 March 2021

24 November 2020

80%+6.0 pts

  • Creek Rise construction site, inspection photo 1, 24 November 2020
  • Creek Rise construction site, inspection photo 2, 24 November 2020
  • Creek Rise construction site, inspection photo 3, 24 November 2020
  • Creek Rise construction site, inspection photo 4, 24 November 2020

31 August 2020

74%+5.9 pts

  • Creek Rise construction site, inspection photo 1, 31 August 2020
  • Creek Rise construction site, inspection photo 2, 31 August 2020
  • Creek Rise construction site, inspection photo 3, 31 August 2020
  • Creek Rise construction site, inspection photo 4, 31 August 2020

11 May 2020

68%+8.1 pts

  • Creek Rise construction site, inspection photo 1, 11 May 2020
  • Creek Rise construction site, inspection photo 2, 11 May 2020
  • Creek Rise construction site, inspection photo 3, 11 May 2020
  • Creek Rise construction site, inspection photo 4, 11 May 2020

29 October 2019

60%+18 pts

  • Creek Rise construction site, inspection photo 1, 29 October 2019
  • Creek Rise construction site, inspection photo 2, 29 October 2019
  • Creek Rise construction site, inspection photo 3, 29 October 2019
  • Creek Rise construction site, inspection photo 4, 29 October 2019

25 July 2019

42%+8.4 pts

  • Creek Rise construction site, inspection photo 1, 25 July 2019
  • Creek Rise construction site, inspection photo 2, 25 July 2019
  • Creek Rise construction site, inspection photo 3, 25 July 2019
  • Creek Rise construction site, inspection photo 4, 25 July 2019

11 April 2019

34%+10 pts

  • Creek Rise construction site, inspection photo 1, 11 April 2019
  • Creek Rise construction site, inspection photo 2, 11 April 2019
  • Creek Rise construction site, inspection photo 3, 11 April 2019
  • Creek Rise construction site, inspection photo 4, 11 April 2019

All 139 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 53% built on average.

The Lagoons Phase One has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Creek Rise?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Creek Rise handover date?
Construction of Creek Rise is recorded as complete, with a registered completion date of June 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Creek Rise?
Creek Rise was 100% built at the site inspection on 29 December 2021. The site has been inspected 15 times since October 2017. The Land Department took 139 site photos at its inspections.
Is Creek Rise delayed?
The register lists construction as complete.
Who is building Creek Rise?
The registered developer is The Lagoons Phase One. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Creek Rise?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.